Customer Meeting (03.11.2016)

bozis edited this page Nov 5, 2016 · 3 revisions
<style> </style> <style> /* Style Definitions */ table.MsoNormalTable {mso-style-name:"Table Normal"; mso-tstyle-rowband-size:0; mso-tstyle-colband-size:0; mso-style-noshow:yes; mso-style-priority:99; mso-style-parent:""; mso-padding-alt:0in 5.4pt 0in 5.4pt; mso-para-margin:0in; mso-para-margin-bottom:.0001pt; mso-pagination:widow-orphan; font-size:10.0pt; font-family:"Times New Roman",serif;} table.MsoTableGrid {mso-style-name:"Table Grid"; mso-tstyle-rowband-size:0; mso-tstyle-colband-size:0; mso-style-priority:59; mso-style-unhide:no; border:solid windowtext 1.0pt; mso-border-alt:solid windowtext .5pt; mso-padding-alt:0in 5.4pt 0in 5.4pt; mso-border-insideh:.5pt solid windowtext; mso-border-insidev:.5pt solid windowtext; mso-para-margin:0in; mso-para-margin-bottom:.0001pt; mso-pagination:widow-orphan; font-size:10.0pt; font-family:"Times New Roman",serif;} </style>

Group 11 Customer Meeting-2

Date: Nov 3, 2016

Time: 14.00 – 15.00

Location: BM A2, Boğaziçi University, Istanbul

 

Meeting called by:


Suzan Üsküdarlı
Ahmet Alp Kındıroğlu
Kaan Bulut Tekelioğlu
Emrah Küçük
Özgür Akyazı
Mustafa Erdoğan
Doğukan Ocak
Mehmet Özdemir
Büşra Öziş

Type of meeting:

Customer Meeting

Timekeeper:

Kaan Bulut Tekelioglu

Note taker:

Kaan Bulut Tekelioğlu

 

Minutes of Meeting

Agenda Item 1: Explaining what is achieved on the internal milestone to the customers
Agenda Item 2: Up-to-dateness of Project Plan
Agenda Item 3: Discussing On How a Project Plan should be prepared
Agenda Item 4: Taking advice from customers about Relationship functionality

Conclusions:

We told our customers that we were a little bit behind according to our plan. Our customer, Suzan Üsküdarlı made a very important critic about our plan not being up-to-date. We should be revising our plan. We had some critics on how tasks in the plan should be splitted. According to these critics, task duration in a plan should be between 12 hours to 48 hours. And tasks should be easy to follow. Also, we had some advices from our customers about relationship functionality. According to these advices, relationships won't be created arbitrarily but they will be created only if they exist in some semantically linked online communities like Ontology, DBPedia, etc.

 

Home

Project Description

Milestone Reports (Fall 2016)

Group 11 Members

  • [Büşra Öziş](Büşra Öziş)
  • [Mehmet Özdemir](Mehmet Özdemir)
  • [Mustafa Doğukan Ocak](Mustafa Doğukan Ocak)
  • [Mustafa Erdoğan](Mustafa Erdoğan)
  • [Özgür Akyazı](Özgür Akyazı)
  • [Sinan Harputluoğlu](Sinan Harputluoğlu)
  • [Emrah Küçük](Emrah Küçük)
  • [Kaan Bulut Tekelioğlu](Kaan Bulut Tekelioğlu)

###Meeting Minutes (Fall 2016)

Customer Meetings (Fall 2016)

Milestone Reports (Spring 2016)

###Meeting Minutes (Spring 2016)

Customer Meetings (Spring 2016)

Internal Instruction Files

Documentation

Clone this wiki locally