Skip to content

Commit

Permalink
jan for feb report
Browse files Browse the repository at this point in the history
  • Loading branch information
womullan committed Mar 26, 2024
1 parent 23982cd commit bc6ff41
Show file tree
Hide file tree
Showing 3 changed files with 204 additions and 57 deletions.
4 changes: 2 additions & 2 deletions Makefile
Original file line number Diff line number Diff line change
Expand Up @@ -43,8 +43,8 @@ index.rst: milestones blockschedule.pdf
@echo ".. include:: acronyms.rst" >> index.rst;

blockschedule.pdf: milestones
python milestones/milestones.py blockschedule --start-date -20
python milestones/milestones.py blockschedule --start-date -20 --output blockschedule.png
python milestones/milestones.py --pmcs-data milestones/data/pmcs/202401-ME.xls blockschedule --start-date -20
python milestones/milestones.py --pmcs-data milestones/data/pmcs/202401-ME.xls blockschedule --start-date -20 --output blockschedule.png

acronyms.rst : myacronyms.txt skipacronyms.txt
generateAcronyms.py -m rst -t "PMO LSST" index.rst
Expand Down
255 changes: 201 additions & 54 deletions index.rst
Original file line number Diff line number Diff line change
@@ -1,4 +1,4 @@
.. Auto-generated by milestones/milestones.py on Tue Mar 26 12:58:10 2024 - DO NOT EDIT
.. Auto-generated by milestones/milestones.py on Tue Mar 26 13:07:58 2024 - DO NOT EDIT
######################
Celebratory Milestones
Expand All @@ -7,63 +7,210 @@ Celebratory Milestones
Provenance
==========

This document was generated based on the contents of the `lsst-dm/milestones <https://github.com/lsst-dm/milestones>`_ repository, version `cd818df9 <https://github.com/lsst-dm/milestones/commit/cd818df949b6250390607f3888a3f7e37ac488b8>`_, dated 2024-03-26.
This corresponds to the status recorded in the project controls system for January 2024.
This document was generated based on the contents of the `lsst-dm/milestones <https://github.com/lsst-dm/milestones>`_ repository, version `0b5c4af9 <https://github.com/lsst-dm/milestones/commit/0b5c4af9195bc035397d971a862444503779799d>`_, dated 2024-03-23.
This corresponds to the status recorded in the project controls system for January 2024. This compares to December 2023.

Key milestones
Top milestones
==============

- **2022-11-30** : Dome Structure enclosed (A1570) **Completed 2022-11-30**
.. list-table::
:header-rows: 1

* - Code
- Name
- Due
- Previously
* - EPOC285
- EPO Construction Finish
- 2022-09-30
- **Completed**
* - T&SC-0400-1730
- TMA Handoff to Rubin
- 2023-03-31
- **Completed**
* - CAMM8090
- COMP: Camera Pre-Ship Review at SLAC
- 2024-04-25
- 2024-03-26
* - SUMMIT-Oct24-160
- ComCam Reinstalled on TMA
- 2024-06-26
- 2024-06-17
* - T&SC-1100-0400
- 3-Mirror Optical System Ready for Testing
- 2024-07-05
- 2024-07-22
* - COMC-060200-20930
- Camera Ready for Full System AI&T
- 2024-10-08
- 2024-09-17
* - T&SC-0400-0950
- Dome Complete
- 2024-12-16
- 2024-12-16
* - SITCOM-122
- LSSTCam Ready for On Sky (First Photon)
- 2025-01-14
- 2025-02-19
* - LSST-1520
- System First Light with LSSTCam
- 2025-02-27
- 2025-04-04
* - LDM-503-17a
- Test report: Final Pipelines Delivery
- 2025-06-25
- 2025-07-31
* - COMC-0654-0430
- COMP: Science Validation Surveys Complete
- 2025-06-25
- 2025-07-31
* - SITCOM-130
- Operation Readiness Review Complete
- 2025-07-02
- 2025-08-07

- **2023-02-01** : Demonstration of CCW control using CSC (Tekniker) - Complete (T&SC-5600-9380) **Completed 2023-02-01**

- **2023-03-20** : Begin TMA Vendor final performance Testing (T&SC-5600-9499) **Completed 2023-03-20**

- **2023-03-27** : Start TMA Science verification (Tekniker/UTE) (T&SC-5600-9445) **Completed 2023-03-27**

- **2023-04-28** : Beneficial Occupancy of Telescope Mount (T&SC-5500-1200) **Completed 2023-04-28**

- **2023-05-31** : Atmospheric Telescope Ready at Summit (T&SC-6800-1463) **Completed 2023-05-31**

- **2023-05-31** : AuxTel Vent Gates upgrade complete (T&SC-6800-4190) **Completed 2023-05-31**

- **2023-05-31** : MCS & IS integration and verification - Complete (T&SC-5600-9090) **Completed 2023-05-31**

- **2023-06-30** : NEED: Pathfinder in ComCam on TMA (SUMMIT-3013) **Completed 2023-06-30**

- **2024-02-01** : Provisional dome rotation deCommissioning (A9290)

- **2024-02-01** : Dome Ready For TMA Science Verification (T&SC-5400-6300)

- **2024-02-02** : ComCam + PF re-Installed on TMA (SITCOM-105)

- **2024-02-16** : Installation of Az Pinion & Gear completed (A9300a)

- **2024-04-25** : LSSTCam Pre-Ship Acceptance (SUMMIT-2975)

- **2024-05-15** : LSSTCam Received @ Summit (SUMMIT-2976)

- **2024-06-24** : Calibration Screen Installation complete (A9370)

- **2024-07-08** : Light Baffle installation Complete (A9360)

- **2024-10-08** : COMP: Camera Reverification Complete (SUMMIT-3056)

- **2024-10-08** : LSSTCam reverification complete (SITCOM-125)

- **2024-11-20** : LSSTCam Installed on TMA (SITCOM-123)

- **2024-12-16** : Installation of Light Windscreen Complete (A9410)

- **2025-01-07** : Camera Ready for Engineering Punchlist Resolution (SITCOM-XXX)

- **2025-01-07** : LSSTCam Cold (New1135)

- **2025-01-29** : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)

- **2025-01-30** : Full focal plane readout complete (New1110)

- **2025-06-25** : COMP: Calibration Products Production Verified (COMC-0654-1000)

A public HTML version for embedding is `here <./top_milestones.html>`_.

Supporting milestones
=====================

.. list-table::
:header-rows: 1

* - Code
- Name
- Due
- Previously
* - LDM-503-11a
- ComCam Ops Readiness
- 2020-12-31
- **Completed**
* - EPO-M6
- User Interfaces Complete
- 2022-09-30
- **Completed**
* - EPOC304
- Citizen Science Commissioning Project running via LSST infrastructure Complete
- 2022-09-30
- **Completed**
* - SITCOM-92
- Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope
- 2022-12-01
- **Completed**
* - LDM-503-13
- Ops rehearsal for data release processing #1
- 2023-02-28
- **Completed**
* - DM-27734
- Completion of the Scheduler
- 2023-06-30
- **Completed**
* - SITCOM-127
- M2 coating decision
- 2023-10-01
- **Completed**
* - LSST4820
- Love Contract Complete
- 2023-11-01
- **Completed**
* - DM-35987
- OCS Available on Summit
- 2024-02-01
- 2024-01-02
* - DM-35989
- TCS Demonstrated
- 2024-02-01
- 2024-01-02
* - SITCOM-102
- TMA safe for transition to M1M3 glass mirror
- 2024-02-01
- 2024-01-02
* - SITCOM-97
- M1M3 cell+Surrogate Dynamic Testing on TMA done
- 2024-02-01
- 2024-02-05
* - SITCOM-105
- ComCam + PF re-Installed on TMA
- 2024-02-02
- 2024-01-03
* - SUMMIT-2976
- LSSTCam Received @ Summit
- 2024-05-15
- 2024-04-23
* - SITCOM-104
- M2 Glass installed on Cell
- 2024-05-15
- 2024-05-23
* - DM-35988
- M2 Software demonstrated
- 2024-06-03
- 2024-05-02
* - SITCOM-109
- M1M3 Mirror Coating completed
- 2024-06-07
- 2024-06-24
* - T&SC-1100-0300
- M2 Installed on Telescope
- 2024-06-20
- 2024-06-11
* - SITCOM-110
- M1M3 installed on the TMA
- 2024-07-05
- 2024-07-22
* - SITCOM-125
- LSSTCam reverification complete
- 2024-10-08
- 2024-09-17
* - SITCOM-123
- LSSTCam Installed on TMA
- 2024-11-20
- 2025-01-29
* - New1135
- LSSTCam Cold
- 2025-01-07
- 2025-02-12
* - SUMMIT-3023
- COMP: TMA Refrigeration Tests Complete
- 2025-01-29
- 2025-01-29
* - New1110
- Full focal plane readout complete
- 2025-01-30
- 2025-03-07
* - New1165
- Telescope Aligned
- 2025-01-31
- 2025-03-10
* - DM-AP-17
- Solar System Processing pipeline (SSP) available.
- 2025-02-27
- 2025-04-04
* - SITCOM-116
- Initial Optical testing on TMA complete
- 2025-02-27
- 2025-04-04
* - SITCOM-121
- System First Light with LSSTCam
- 2025-02-27
- 2025-04-04
* - COMC-0140
- Start SV Data Collection
- 2025-04-04
- 2025-05-12
* - DM-AP-16
- Full integration of the Alert Production system within the operational environment.
- 2025-06-25
- 2025-07-31
* - LDM-503-16
- Ops rehearsal for data processing #3
- 2025-07-02
- 2025-08-07


.. image:: blockschedule.png
:alt: Block Schedule

`Download the PDF of this Block Schedule here. <./blockschedule.pdf>`_