Skip to content

Commit

Permalink
Merge pull request #87 from lsst-dm/tickets/DM-42601
Browse files Browse the repository at this point in the history
table format
  • Loading branch information
womullan authored Feb 15, 2024
2 parents b0c1e88 + e30424c commit 9191ca5
Show file tree
Hide file tree
Showing 3 changed files with 203 additions and 101 deletions.
7 changes: 7 additions & 0 deletions .pre-commit-config.yaml
Original file line number Diff line number Diff line change
@@ -0,0 +1,7 @@
repos:
- repo: https://github.com/pre-commit/pre-commit-hooks
rev: v4.5.0
hooks:
# - id: trailing-whitespace
- id: check-yaml
- id: check-toml
8 changes: 1 addition & 7 deletions Makefile
Original file line number Diff line number Diff line change
Expand Up @@ -34,13 +34,7 @@ clean:
# celeb uses fdue forecast dates
.PHONY:
index.rst: milestones blockschedule.pdf
python milestones/milestones.py celeb --inc=Y ;
mv index.rst temp.rst;
@echo "======================" > index.rst;
@echo "Celebratory Milestones" >> index.rst;
@echo "======================" >> index.rst;
cat temp.rst >> index.rst;
rm temp.rst;
python milestones/milestones.py celeb --inc=Y --months=1 --table ;
@echo ".. image:: blockschedule.png" >> index.rst;
@echo " :alt: Block Schedule" >> index.rst;
@echo "" >> index.rst;
Expand Down
289 changes: 195 additions & 94 deletions index.rst
Original file line number Diff line number Diff line change
@@ -1,109 +1,210 @@
======================
Celebratory Milestones
======================
.. Auto-generated by milestones/milestones.py on Mon Jan 22 15:53:54 2024 - DO NOT EDIT
.. Auto-generated by milestones.py on Wed Jan 24 17:44:32 2024 - DO NOT EDIT
:tocdepth:
######################
Celebratory Milestones
######################

Provenance
==========

This document was generated based on the contents of the `lsst-dm/milestones <https://github.com/lsst-dm/milestones>`_ repository, version `88ac8705 <https://github.com/lsst-dm/milestones/commit/88ac870528ca1004023d8bb9a8fbb5afc971fcce>`_, dated 2023-10-17.
This corresponds to the status recorded in the project controls system for September 2023.
This document was generated based on the contents of the `lsst-dm/milestones <https://github.com/lsst-dm/milestones>`_ repository, version `bccc2d19 <https://github.com/lsst-dm/milestones/commit/bccc2d19969410467bebedd28c6b88053299cc60>`_, dated 2024-01-24.
This corresponds to the status recorded in the project controls system for December 2023.
This compares October 2023 data to December 2023.

Top milestones
==============

- **2022-09-30** : EPO Construction Finish (EPOC285) **Completed 2022-09-30**

- **2023-03-31** : TMA Handoff to Rubin (T&SC-0400-1730) **Completed 2023-03-31**

- **2024-02-21** : COMP: Camera Pre-Ship Review at SLAC (CAMM8090)

- **2024-05-29** : ComCam Reinstalled on TMA (SUMMIT-Oct24-160)

- **2024-07-01** : Dome Complete (T&SC-0400-0950)

- **2024-07-03** : 3-Mirror Optical System Ready for Testing (T&SC-1100-0400)

- **2024-08-28** : Camera Ready for Full System AI&T (COMC-060200-20930)

- **2024-12-11** : LSSTCam Ready for On Sky (First Photon) (SITCOM-122)

- **2025-01-24** : System First Light with LSSTCam (LSST-1520)

- **2025-05-22** : Test report: Final Pipelines Delivery (LDM-503-17a)

- **2025-05-22** : COMP: Science Validation Surveys Complete (COMC-0654-0430)

- **2025-05-29** : Operation Readiness Review Complete (SITCOM-130)
.. list-table::
:widths: 5 10 12 12
:header-rows: 1

* - Code
- Name
- Due
- Previously
* - EPOC285
- EPO Construction Finish
- 2022-09-30
- **Completed**
* - T&SC-0400-1730
- TMA Handoff to Rubin
- 2023-03-31
- **Completed**
* - CAMM8090
- COMP: Camera Pre-Ship Review at SLAC
- 2024-03-26
- 2024-03-05
* - SUMMIT-Oct24-160
- ComCam Reinstalled on TMA
- 2024-06-17
- 2024-05-30
* - T&SC-0400-0950
- Dome Complete
- 2024-07-01
- 2024-07-01
* - T&SC-1100-0400
- 3-Mirror Optical System Ready for Testing
- 2024-07-22
- 2024-07-04
* - COMC-060200-20930
- Camera Ready for Full System AI&T
- 2024-09-27
- 2024-08-29
* - SITCOM-122
- LSSTCam Ready for On Sky (First Photon)
- 2025-01-03
- 2024-12-12
* - LSST-1520
- System First Light with LSSTCam
- 2025-02-18
- 2025-01-27
* - LDM-503-17a
- Test report: Final Pipelines Delivery
- 2025-06-16
- 2025-05-23
* - COMC-0654-0430
- COMP: Science Validation Surveys Complete
- 2025-06-16
- 2025-05-23
* - SITCOM-130
- Operation Readiness Review Complete
- 2025-06-23
- 2025-05-30

A public HTML version for embedding is `here <./top_milestones.html>`_.

Supporting milestones
=====================

- **2020-12-31** : ComCam Ops Readiness (LDM-503-11a) **Completed 2020-12-31**

- **2022-09-30** : User Interfaces Complete (EPO-M6) **Completed 2022-09-30**

- **2022-09-30** : Citizen Science Commissioning Project running via LSST infrastructure Complete (EPOC304) **Completed 2022-09-30**

- **2022-12-01** : Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope (SITCOM-92) **Completed 2022-12-01**

- **2023-02-28** : Ops rehearsal for data release processing #1 (LDM-503-13) **Completed 2023-02-28**

- **2023-06-30** : Completion of the Scheduler (DM-27734) **Completed 2023-06-30**

- **2023-10-02** : OCS Available on Summit (DM-35987)

- **2023-10-02** : TCS Demonstrated (DM-35989)

- **2023-10-02** : TMA safe for transition to M1M3 glass mirror (SITCOM-102)

- **2023-11-08** : M1M3 cell+Surrogate Dynamic Testing on TMA done (SITCOM-97)

- **2023-11-09** : ComCam + PF re-Installed on TMA (SITCOM-105)

- **2023-12-01** : Love Contract Complete (LSST4820)

- **2024-01-17** : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)

- **2024-03-29** : M2 Software demonstrated (DM-35988)

- **2024-04-04** : LSSTCam Received @ Summit (SUMMIT-2976)

- **2024-05-06** : M2 coating decision (SITCOM-127)

- **2024-05-06** : M2 Glass installed on Cell (SITCOM-104)

- **2024-05-23** : M2 Installed on Telescope (T&SC-1100-0300)

- **2024-07-03** : M1M3 installed on the TMA (SITCOM-110)

- **2024-08-28** : LSSTCam reverification complete (SITCOM-125)

- **2024-10-17** : LSSTCam Installed on TMA (SITCOM-123)

- **2024-12-04** : LSSTCam Cold (New1135)

- **2024-12-27** : Full focal plane readout complete (New1110)

- **2024-12-30** : Telescope Aligned (New1165)

- **2025-01-24** : Solar System Processing pipeline (SSP) available. (DM-AP-17)

- **2025-01-24** : Initial Optical testing on TMA complete (SITCOM-116)

- **2025-03-03** : Start SV Data Collection (COMC-0140)

- **2025-05-22** : Full integration of the Alert Production system within the operational environment. (DM-AP-16)

- **2025-05-29** : Ops rehearsal for data release processing #3 (LDM-503-16)

.. image:: blockschedule.png
:alt: Block Schedule

`Download the PDF of this Block Schedule here. <./blockschedule.pdf>`_

.. include:: acronyms.rst
.. list-table::
:widths: 15 30 12 12
:header-rows: 1

* - Code
- Name
- Due
- Previously
* - LDM-503-11a
- ComCam Ops Readiness
- 2020-12-31
- **Completed**
* - EPO-M6
- User Interfaces Complete
- 2022-09-30
- **Completed**
* - EPOC304
- Citizen Science Commissioning Project running via LSST infrastructure Complete
- 2022-09-30
- **Completed**
* - SITCOM-92
- Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope
- 2022-12-01
- **Completed**
* - LDM-503-13
- Ops rehearsal for data release processing #1
- 2023-02-28
- **Completed**
* - DM-27734
- Completion of the Scheduler
- 2023-06-30
- **Completed**
* - SITCOM-127
- M2 coating decision
- 2023-10-01
- **Completed**
* - LSST4820
- Love Contract Complete
- 2023-11-01
- **Completed**
* - DM-35987
- OCS Available on Summit
- 2024-01-02
- 2023-11-01
* - DM-35989
- TCS Demonstrated
- 2024-01-02
- 2023-11-01
* - SITCOM-105
- ComCam + PF re-Installed on TMA
- 2024-01-03
- 2023-11-03
* - SITCOM-102
- TMA safe for transition to M1M3 glass mirror
- 2024-01-08
- 2024-01-08
* - SITCOM-97
- M1M3 cell+Surrogate Dynamic Testing on TMA done
- 2024-02-05
- 2023-12-15
* - SUMMIT-2976
- LSSTCam Received @ Summit
- 2024-04-23
- 2024-04-05
* - DM-35988
- M2 Software demonstrated
- 2024-05-02
- 2024-03-29
* - SUMMIT-3023
- COMP: TMA Refrigeration Tests Complete
- 2024-05-08
- 2024-04-11
* - SITCOM-104
- M2 Glass installed on Cell
- 2024-05-23
- 2024-05-07
* - T&SC-1100-0300
- M2 Installed on Telescope
- 2024-06-11
- 2024-05-24
* - SITCOM-109
- M1M3 Mirror Coating completed
- 2024-06-24
- 2024-06-06
* - SITCOM-110
- M1M3 installed on the TMA
- 2024-07-22
- 2024-07-04
* - SITCOM-125
- LSSTCam reverification complete
- 2024-09-27
- 2024-08-29
* - SITCOM-123
- LSSTCam Installed on TMA
- 2024-11-11
- 2024-10-18
* - New1135
- LSSTCam Cold
- 2024-12-27
- 2024-12-05
* - New1110
- Full focal plane readout complete
- 2025-01-21
- 2024-12-30
* - New1165
- Telescope Aligned
- 2025-01-22
- 2024-12-31
* - DM-AP-17
- Solar System Processing pipeline (SSP) available.
- 2025-02-18
- 2025-01-27
* - SITCOM-116
- Initial Optical testing on TMA complete
- 2025-02-18
- 2025-01-27
* - SITCOM-121
- System First Light with LSSTCam
- 2025-02-18
- 2025-01-27
* - COMC-0140
- Start SV Data Collection
- 2025-03-26
- 2025-03-04
* - DM-AP-16
- Full integration of the Alert Production system within the operational environment.
- 2025-06-16
- 2025-05-23
* - LDM-503-16
- Ops rehearsal for data processing #3
- 2025-06-23
- 2025-05-30