This document was generated based on the contents of the lsst-dm/milestones repository, version 0fb8b61e, dated 2024-03-23. This corresponds to the status recorded in the project controls system for February 2024.
Throughout this document, the identifiers of completed milestones are set in italics; those of milestones which are still pending, in roman.
The DM Subsystem is currently tracking 388 milestones: 7 at Level 1, 84 at Level 2, 272 at Level 3, and 23 at Level 4. 2 have no level defined. Of these, 356 have been completed. Of the incomplete milestones, 9 are late relative to the baseline schedule, while the remainder are scheduled for the future.
There are 9 milestones overdue as of 2024-03-23 13:41:58.167641.
- LDM-503-18q: Qserv construction complete [Due 2024-01-11]
- LDM-503-EFDb: EFD/telemetry data replicated at the LDF, stored in InfluxDB. aggregated into parquet files [Due 2023-06-16]
- DM-DRP-27: Object generation: association and assembly of (DIA, coadd, etc) sources to form objects. [Due 2021-08-31]
- DM-DRP-37: Artifact rejection and background matching during coadd construction. [Due 2018-11-30]
- DM-DAX-15: DAX Construction Complete [Due 2024-01-11]
- DM-SQRE-4: Notebook service ready for verification & validation [Due 2023-02-28]
- DMTC-021101-1155: COMP: Encryption [Due 2023-12-07]
- DMTC-021102-1175: COMP: Firewalls and Physical Security [Due 2023-12-06]
- DMTC-021103-1085: COMP: Delayed Data Store Installed [Due 2023-11-28]
- DMTC-6800-1350: Network End-to-End Verification Test
- DM-SQRE-5: Notebook service ready for general science users
- LDM-503-17a: Test report: Final Pipelines Delivery
- DM-READY: DM is ready for ORR
- LDM-503-19: All 1a,1b DM requirements verified
- DM-AP-14: Alert filtering system available.
- DM-AP-16: Full integration of the Alert Production system within the operational environment.
- No milestones due.
- DLP-526: Archive Center Integration Complete at SLAC
- LDM-503-17: Final operations rehearsal
- LDM-503-RSPb: Science Platform ready for Science Verification
- DM-NCSA-21: L1 Offline Processing Service, Raft Scale, ComCam
- LDM-503-12: Ops rehearsal for commissioning #3
- LDM-503-14: Test report: DM Readiness for Science Verification Surveys
- LDM-503-16: Ops rehearsal for data processing #3
- LDM-503-12a: LSSTcam On Sky Readiness
- LDM-503-EFDc: EFD data is queriable through TAP in the Science Platform
- RSP-1200: RSP handles 1200 users
- LDM-503-19a: All P1a DM requirements verified
- DM-AP-15: Alert distribution system fully integrated.
- DM-AP-17: Solar System Processing pipeline (SSP) available.
- DM-DRP-24: Physically motivated PSF model, including separate characterization of contributions from the atmosphere and the telescope system.
- DM-DRP-31: A photometric redshift is now provided for each object.
- DM-DRP-36: Solar System Processing integrated to data release processing.
- DM-DAX-9: Butler Provenance System
- No milestones due.
- No milestones due.
- No milestones due.
- LDM-503-15: Ops rehearsal for data release processing #2
- No milestones due.
- LDM-503-16a: Test report: Pipelines Release Spring 2023
- LDM-503-13: Ops rehearsal for data release processing #1
- LDM-503-NET: Network Verification End-to-End
- No milestones due.
- NET-neutral: Cisco ACI replaced
- LDM-503-18q: Qserv construction complete
- DM-DAX-15: DAX Construction Complete
- DMTC-021101-1155: COMP: Encryption
- DMTC-021102-1175: COMP: Firewalls and Physical Security
- DMTC-021103-1085: COMP: Delayed Data Store Installed
- No milestones due.
- No milestones due.
- No milestones due.
- No milestones due.
- LDM-503-EFDa: Engineering Facility Database at the summit capturing and enabling access to all telemetry with M1/M3 active
- LDM-503-EFDb: EFD/telemetry data replicated at the LDF, stored in InfluxDB. aggregated into parquet files
- No milestones due.
- No milestones due.
- No milestones due.
- DM-SQRE-4: Notebook service ready for verification & validation
- No milestones due.
- No milestones due.
- No milestones due.
- A9440: START: Data Security
- LDM-503-RSPa: Science Platform ready for DP0.2 with Image Services
- No milestones due.
- No milestones due.
- No milestones due.
- S22F: S22 Complete
- LDM-503-15a: Test report: Pipelines Release Spring 2022
- No milestones due.
- No milestones due.
- No milestones due.
- No milestones due.
- S22S: S22 Start
- DM-PORTAL: Resume development of LSP portal aspect
- DM-CLOUD: Decide on final data facility design for DR1
- F21F: F21 Complete
- No milestones due.
- DMTC-8100-2450: FIU-CIARA Management Contract Delivery #7 Complete
- LDM-GEN3: Gen3 parity demonstrated
- LDM-503-13a: Test report: Pipelines Release Fall 2020
- DM-AP-12: Difference imaging is now agnostic to the PSF of the template image.
- DM-AP-13: Trailed source measurement on difference images.
- DM-DRP-26: Overlap resolution at tract & patch boundaries.
- DM-DRP-27: Object generation: association and assembly of (DIA, coadd, etc) sources to form objects.
- DM-DRP-28: Difference images are now a first-class data product during data release processing.
- DM-DRP-35: Simultaneous measurement across a suite of coadds representing different bandpasses, epocs, and flavors.
- No milestones due.
- DMTC-8100-2210: 100G ring operating at 99.99% availability - Complete
- F21S: F21 Start
- DM-DRP-23: Atmospheric characterization based on data from the Auxiliary Telescope now available.
- S21S: S21 Start
- No milestones due.
- No milestones due.
- LDM-503-11: Ops rehearsal for commissioning #2
- DM-NET-5: Base - Archive Network Functional 100 Gbps
- DLP-464: Install networking for normal Base Center operations for ComCam scale
- DLP-466: Install networking for ComCam-scale Chilean DAC serving on order 20 people
- LDM-503-09: Test report: Ops rehearsal for commissioning #1
- LDM-503-11b: Test report: Pipelines Release Fall 2019
- LDM-503-14a: Science Platform ready for DP0
- DM-NCSA-15: Batch Processing Service for offline spectrograph data processing
- DM-NCSA-22: Information in consolidated database available to QA portal
- DLP-465: Install networking for normal Base Center operations for full-camera scale
- DLP-468: Provide networking for formal Chilean DAC production at full-camera scale
- DLP-467: Install networking for full-camera-scale Chilean DAC serving on order 80 people
- F20F: F20 Complete
- LDM-503-08: Test report: Spectrograph data acquisition
- LDM-503-10: Test report: DAQ validation
- LDM-503-11a: ComCam Ops Readiness
- DM-DRP-12: Background estimation over the full visit.
- DM-DRP-13: PSF estimation over the full visit.
- DM-DRP-15: All varieties of coadd required for object detection and characterization are now produced during normal pipeline operation (although not necessarily at the ultimately required level of fidelity).
- DM-DRP-21: Integrated image characterization pipeline for Data Release Production.
- DM-DRP-30: Forced photometry is now performed on individual processed visit images during data releases.
- DM-DRP-34: Selection maps are generated during data releases.
- DM-DAX-7: Generation 3 Butler, running on a POSIX file-system provided by NCSA
- DM-DAX-8: Scatter-gather support in PipelineTask
- DM-DAX-12: Generation 3 middleware at feature parity with Generation 2
- DM-DAX-14: Provenance system review completed
- DM-SQRE-6: IVOA Server-side Operations for Data Access API
- DM-SQRE-7: IVOA-compliant image metadata services
- No milestones due.
- DLP-46: Full Capacity over Diverse path Ready
- DMTC-8000-0990: Full capacity La Serena to Santiago over Primary link AND Secondary link - Complete
- DMTC-8100-2410: FIU-CIARA Management Contract Delivery #6 Complete
- DLP-33: Santiago - Boca Raton Full Integration Ready
- DMTC-6800-1325: Network Verification Pre-Tests
- No milestones due.
- DMTC-8100-2170: 100G ring operating at 99.0% availability - Complete
- DM-NCSA-14: Data Backbone endpoints in Chile for ingestion and access, distribution over WAN, ingest at NCSA into custodial file sto
- F20S: F20 Start
- DM-AP-10: Advanced single frame measurement pipeline for Alert Production.
- DM-DRP-22: Template generation integrated with Data Release Production pipelines.
- DLP-533: Base Center Integration Complete
- S20F: S20 Complete
- LDM-503-05: Test report: Alert distribution validation
- LDM-503-06: Test report: DM ComCam interface verification readiness
- LDM-503-10b: Large Scale CCOB Data Access
- LDM-503-09a: Test report: Pipelines Release Fall 2018
- DM-AP-6: Alert format defined & queue system available.
- DM-AP-18: Alert packet generation
- No milestones due.
- No milestones due.
- DM-SQRE-3: Notebook service stable for commissioning and other internal project users
- A6150: Start Milestone: January 1st, 2020
- DM-DRP-8: Calibration product generation for the Auxiliary Telescope.
- S20S: S20 Start
- F19F: F19 Complete
- DM-STAFF: Staffing Checkpoint
- LDM-503-08b: Small Scale CCOB Data Access
- DM-AP-11: Difference imaging includes noise decorrelation and correction for differential chromatic refraction.
- DM-DRP-20: Refined set of LSST calibration products.
- A1300: Start Milestone: October 1st, 2019
- DLP-70: Miami - Chicago Early Integration Ready
- DLP-69: Boca Raton - Chicago Early Integration Ready
- DMTC-8200-0600: ESNet Implementation Phase 1- Complete
- DM-NCSA-20: ComCam Archiving Service
- DMTC-8100-2370: FIU-CIARA Management Contract Delivery #5 Complete
- A4670: June 2019 Travel to Chile - Travel Start
- A4680: June 2019 Travel to Chile - Travel End
- A4750: Summit AA Systems Installed at the Summit
- A4860: ComCam Systems in Tucson ready for NCSA
- DLP-552: LSST Software Release 9.1 Complete, Ready for Full Camera
- DM-NCSA-11: Verified acquisition of raw and crosstalk-corrected exposures at raft scale, incl. correct metadata
- A4369.9: Ship Hardware to BDC
- IT-725-M: Base Data Center Network Complete
- DM-NET-4: Base LAN installed
- LDM-503-10a: Science Platform: TAP service with federated SSO A&A
- A2330: Ship AA System to Chile
- A4640: Ship ComCam Hardware to Tucson
- DMTC-8000-0950: Technical Implementation Plan for 40Gbps diverse path - Complete
- F19S: F19 Start
- DM-NCSA-13: Header Writing Service for Spectrograph use case
- A5090: Expected Arrival of ComCam Systems to NCSA
- IT-716-M2: Furniture installed in Offices, purchased cabling received
- DMTC-8100-2130: 100G ring operating at 98.0% availability - Complete
- S19F: S19 Complete
- DM-SUIT-7: Mapping between SUIT systems & NCSA auth system
- DM-SUIT-10: SUIT deployment procedure
- DLP-36: Santiago - Miami Early Integration Ready
- DMTC-8100-2112: Miami - Boca Raton path diverse fiber - Complete
- DM-NCSA-16: Perform ISR processing on ComCam-scale data.
- DMTC-8000-0870: Report on functional fiber, including uptime, 1st year functional milestone - Complete
- DM-NCSA-3: Provide database for metadata, provenance, location and demonstrate ingest at small scale
- DM-NCSA-4: Minimal support for the small operational schema including file metadata and provenance for every file, and record of in
- IT-718-M: Base Center Full Occupancy
- LDM-503-02: Test report: HSC reprocessing
- LDM-503-04: Test report: Aux Tel DAQ integration functionality test
- LDM-503-07: Test report: Camera data processing
- LDM-503-04b: Test report: Aux Tel DAQ interface Integration Verification and Spectrograph Operations Rehearsal
- DM-SUIT-5: Search and display processed HSC data
- DM-DRP-2: Basic visualization and quality assessment tools operational on HSC-scale data volumes.
- DM-DRP-11: Pipelines code provides supports for database ingestion of results.
- DM-DAX-5: Database ingest in support of HSC reprocessing (ie, large catalog ingest)
- DM-AP-8: Advanced ISR, including ghost and linear feature masking, correction for the Brighter-Fatter effect and compensation for pixel response non-uniformity.
- S19S: S19 Start
- IT-716-M: Base Center Beneficial Occupancy
- F18F: F18 Complete
- DM-SUIT-8: SUIT portal integrated with workspace
- DM-DRP-19: QA metrics are generated during pipeline execution.
- DM-DRP-37: Artifact rejection and background matching during coadd construction.
- DM-DRP-29: Moving point source model fitting now available.
- DM-DAX-10: Per-object gather support in Butler
- DM-SQRE-2: Notebook service capabilities are suitable for the commissioning team to develop notebooks for its needs
- DMTC-8100-2330: FIU-CIARA Management Contract Delivery #4 Complete
- DMTC-8100-2530: Data passing test report - Complete
- DM-DRP-9: Data reduction pipeline for the Auxiliary Telescope.
- DM-NCSA-10: Sustained archiving service that is OCS commandable
- DM-NET-3: Initial Network Ready (Summit)
- DMTC-8200-0510: ESNet Request - Complete
- DM-NET-6: Summit LAN installed
- DM-NCSA-9: Test instance of alert distribution hosting service and L1 database in Development & Integration Enclave
- DLP-551: LSST Software Release 8.1 Complete, Ready for Commissioning Camera
- DM-AP-9: JOINTCAL1: Jointcal at a functional level
- DM-DRP-7: Coordinate transformation tool provided for use with the Collimated Beam Projector.
- DM-DRP-17: Simultaneous photometric and astrometric fitting to multiple exposures.
- DMTC-8100-2090: 100G ring operating at 97.0% availability - Complete
- F18S: F18 Start
- DM-AP-7: Basic instrument signature removal (ISR) capability.
- DM-DRP-3: PSF-homogenized coadd construction.
- DM-DRP-5: Camera package supporting the LSST Camera.
- DM-DRP-38: Camera package supporting the Commissioning Camera.
- DMTC-8000-0836: La Serena to Santiago with live traffic and uptime over LSST Lambda Ready - Complete
- S18F: S18 Complete
- DMTC-8100-2490: First light test report - Complete Contract
- DM-NCSA-5: Level 1 archiving system able to acquire pixel data from the Aux Tel DAQ, header metadata via OCS, assemble FITS image,
- DM-NCSA-6: Ability to transfer files originating from Tucson to NCSA and ingest files at NCSA, including metadata and provenance
- DM-NCSA-7: Capability to paint displays for Tucson and NCSA
- DM-NET-2: Mountain - Base Network Functional 2 x 100 Gbps
- DLP-61: La Serena – Santiago link Ready
- DLP-44: La Serena to Santiago with test traffic AURA DWDM LSST Fiber
- DMTC-8000-0826: Intermediate traffic testing and report - Complete
- DLP-40: Summits-Gatehouse Initial Capability Ready
- DLP-65: Mountain - Base LSST and AURA DWM End Node Installation and Test Ready
- DM-DRP-32: Object classification system available.
- DM-DAX-11: Transformed EFD schema
- No milestones due.
- DM-DRP-16: Global photometric fitting (e.g. Burke et al. Forward Global Calibration Method).
- DM-NCSA-27: Deliver header service code
- DM-NCSA-29: Deliver IIP image client code
- DMTC-4500-0010: Start NCSA S18
- S18S: S18 Start
- LSST-1160: Header Service Integration
- LSST-1190: Control Interfaces Verification: Single Visit
- LSST-1200: Interface Verification: Single Visit
- LSST-1220: EFD ETL Under DM Control
- DLP-837: AP-ready Butler Framework
- DLP-864: Coordination with NCSA/CC-IN2P3 JCC
- DLP-368: Initial AP DMCS
- DLP-459: Qserv capability to hold data reduced at NCSA
- DLP-458: Ingest of bulk data from real cameras to ComCam scale
- DLP-457: Support runs on real cameras data and ImSim data
- DLP-442: Procure infrastructure for Base Center to meet FY18 goals
- DLP-433: Procure infrastructure for Archive Center to FY18 scale
- DMTC-8000-0818: Acceptance Test with Equipment Installed - Complete
- DMTC-7400-2510: REUNA La Serena - Santiago Optical Channel in operation - Complete
- DMTC-7400-2130: End of commissioning. Acceptance of fiber connection - Complete
- F17F: F17 Complete
- LDM-503-01: Test report: Science Platform with WISE data in PDAC
- LDM-503-03: Test report: Alert generation validation
- DM-SUIT-1: Search and display WISE sources (objects) in PDAC
- DM-SUIT-4: Multiple data traces in chart space
- DLP-207: Extra LSST query capabilities in web UI
- DLP-205: LSST web UI search external catalog
- DLP-222: Provide time-domain data view
- DM-DRP-14: Insertion of simulated sources into the data stream to check pipeline performance.
- DM-DRP-18: Initial multi-band deblending algorithm available.
- DM-DAX-1: WISE data ingest to PDAC
- DM-DAX-6: Prototype level 1 database
- DLP-473: Async Queries in Qserv
- DLP-725: Working Prototype of AP/L1 Database
- DLP-344: Release SQuaSH-in-a-box automated deployment platform
- DLP-352: Metrics of Interest integrated in running stack or post-tests
- DMTC-7400-2480: AURA DWDM equipment in operation - Complete
- DM-NCSA-28: IIP control code
- DMTC-7400-2330: LSST and AURA summit to base DWDM equipment - Complete
- DMTC-8100-2290: FIU-CIARA Management Contract Delivery #3 Complete
- DMTC-7400-2090: Report on functional fiber connections, including AURA equipment - Complete
- DLP-558: LSST Software Release 7.1 Complete
- DM-AP-1: Basic single frame measurement pipeline.
- DM-AP-2: Alard & Lupton-style image differencing.
- DM-AP-3: Point source & dipole measurement on difference images.
- DM-AP-4: DIASource association
- DM-AP-5: DIAObject generation
- DM-DRP-6: Camera package supporting the Auxiliary Telescope.
- DM-SQRE-1: Project internal Jupyter notebook service
- DMTC-7400-2420: REUNA La Serena - Santiago DWDM equipment - Complete
- DM-SUIT-2: Search WISE coaded data single exposure images in PDAC (the images are from IRSA at IPAC, not NCSA)
- DM-DAX-2: Query service supporting IVOA TAP protocol, w/ support for asynchronous queries
- DMTC-7400-2250: End of commissioning and Acceptance - Complete
- DMTC-8100-2474: Agreement with Monet Cable Partner signed Complete
- F17S: F17 Start
- DM-NCSA-1: Provide regular reprocessing service for HSC data
- DM-NCSA-2: Provide access to results of regular reprocessing (NB the form this takes depends upon available DAX functionality)
- DLP-538: LSE-130 Data items Exchanged between Cam & DM - Phase 3
- DMTC-0000-3000: LSST Software Release S17 Complete
- S17F: S17 Complete
- DM-DRP-1: HSC merger complete: all functionality deployed for the most recent HSC data release processing is now available within the LSST stack.
- DM-DRP-4: Calibration product generation in support of basic ISR.
- DLP-736: Performance and capability enhancements in support of catalog use cases
- DLP-152: Initial PSF-matched image coaddition available
- DLP-472: Qserv Data Distribution
- DMTC-8200-0480: VLAN design finalized Miami-NCSA - Complete
- No milestones due.
- DLP-37: Summits-Gatehouse Fiber Ready
- DMTC-7400-2210: Fiber delivery by Telefonica - Complete
- DLP-567: LSST Software Release 7.0 Complete
- DMTC-8000-0806: 3T Fiber Installation Certification and Acceptance Test - Complete
- S17S: S17 Start
- DLP-847: Meet camera DAQ/OCS milestones for FY16
- DLP-366: Mid-scale processing of eligible camera data
- DLP-412: Monitor development cluster
- DMTC-0000-0030: LSST Software Release F16 Complete
- DLP-871: Firefly server side code refactor
- DLP-802: Alert Production Database (APDB) design
- No milestones due.
- DMTC-8100-2050: 100G ring operating at 95.0% availability - Complete
- DMTC-8100-2250: FIU-CIARA Management Contract Delivery #2 Complete
- DLP-544: LSE-72 OCS-DM master interface - Phase 3
- DM-SUIT-3: Time series analysis tool for WISE data
- DLP-557: LSST Software Release 6.1 Complete
- DLP-579: Usability and developer efficiency
- DLP-346: SQuaSH Prototype using existing architectural components deployed
- DLP-541: LSE-68 Camera-DM Image data interfaces - Phase 3
- DLP-63: Vendor selection Ready
- DMTC-7400-2290: Final Selection of equipment vendor - Complete
- DMTC-0000-0020: LSST Software Release X16 Complete
- DLP-694: Prototype Brighter-Fatter correction available
- DLP-45: Delivery of "functional Pre-operations Link" (at least 4Gbps), Ready
- DMTC-8000-0910: Delivery of 4Gbs link from La Serena to Santiago Ready - Complete
- DMTC-7400-2050: Fiber delivery - Complete
- DLP-469: Coordination with NCSA/CC-IN2P3 JCC
- DLP-358: Refinement of facility integration plan and traceability of science and operational requirements
- DLP-364: Build prototype production sequence for the DMCS
- DLP-850: Prototype authentication/authorization system complete
- DLP-405: Investigate CAS integration with Internet2 AAA tools
- DLP-411: Monitor OpenStack
- DLP-424: Integration of DevOps to OpenStack
- DLP-471: Refresh sizing model
- DLP-431: Refinement of facility integration plan and traceability of science and operational requirements
- DLP-566: LSST Software Release 6.0 Complete
- DLP-872: Convert major portion of GWT in Firefly to pure JavaScript
- DLP-486: Prototype merge & deduplication in tract & patch overlaps
- DLP-103: Prototype multi-coadd peak association available
- DLP-100: Consistent multi-band deblending available
- DLP-649: Shared Scans
- DLP-345: Prototype metrics collection system deployed
- DLP-351: Intermediate Performance Metrics routinelly calculated and published
- DLP-337: Release new stack documentation infrastructure
- DLP-452: Support datasets on basic file system infrastructure with apropos policies
- DLP-41: Mountain - Base Fiber Path Ready
- DMTC-7400-2170: Gatehouse to Summit contract signed; Design Ready - Complete
- DLP-276: Dipole measurement suite
- DLP-43: Fiber Delivery Ready
- DMTC-8000-0760: Technical Implementation plan of fiber connection (primary link) - Complete
- DMTC-7400-0815: La Serena-Gatehouse path design Ready
- DMTC-7400-2010: Gatehouse to La Serena path design Ready - Complete
- DLP-288: HSC merger complete
- DLP-700: Galaxy shear fitting parameters available
- DLP-342: Publish updated introductory software guide to developing with the stack
- DLP-341: Deploy stack user support and discussion forum
- DLP-101: Prototype coadd detection available
- DLP-73: Footprints redesigned and refactored
- DLP-635: Qserv Query Cancellation
- DMTC-8100-2010: First Data passed on 100G ring without errors - Complete
- DLP-528: Archive Site Ready for Equipment Configuration
- DLP-275: Deliver document on effects of DCR
- DLP-805: Distributed Database and Table Management
- DLP-357: Initial refinement of facility integration plan
- DLP-389: Implement advanced logging functionality, including event-based logging
- DLP-42: La Serena to Santiago Path Design Ready
- DLP-356: Set up Joint Coordination Council (JCC) for coordination with satellite processing center
- DLP-355: Establish MOA with CC-IN2P3 satellite processing center
- DLP-361: Build prototype AP DMCS, including events
- DLP-404: Identify candidate security packages
- DLP-410: Implement Puppet for system configuration management
- DLP-415: Evaluate iRODS, Datacat, and similar file system management technologies
- DLP-423: DevOps assessment
- DLP-430: Initial refinement of facility integration plan
- DLP-556: LSST Software Release 5.1 Complete
- DLP-218: Provide API for image display in Firefly
- DLP-216: Provide basic APIs to use Firefly visualization components
- DLP-503: Prototype direct coaddition
- DLP-502: Prototype image artifact identification available
- DLP-25: Prototype Web Service for SUI
- DLP-340: Operating system testing for public stack releases increased
- DLP-334: SQuaRE release improved or changed CI system
- DLP-451: Deploy OpenStack capability
- DLP-256: First draft definition of workspace
- DLP-564: Able to use some data-access APIs developed by database team
- DLP-400: Refactor basic event services
- DLP-441: Base Center requirements document
- DLP-817: Multi-node Multi-query Integration Testing Harness
- DLP-800: Data Ingest into MySQL
- No milestones due.
- DLP-518: Evaluate best-of-breed tools. Technology exploration.
- DLP-521: Define the data access APIs with database team
- DLP-450: Support lsst-dev for developers
- DLP-449: Upgrade storage server hardware
- DLP-555: LSST Software Release 5.0 Complete
- DLP-644: Generalized Single Frame Astrometry Pipeline
- DLP-422: Evaluate OpenStack as a development environment
- DLP-360: Prepare for OCS Middleware integration with AP DMCS
- DLP-359: Improve fault tolerance in AP simulator
- DLP-818: CSS
- DLP-801: Qserv uses C++-based Geometry Code
- DLP-519: Research the development framework for SUI
- DLP-554: LSST Software Release 4.0 Complete
- DLP-724: Forced per-epoch photometry
- DLP-716: Fundamental flux measurements
- DLP-578: Propose a workspace structure for discussion.
- DLP-574: Evaluate best-of-breed tools. Technology exploration.
- DLP-575: Evaluate best-of-breed tools. Technology exploration.
- DLP-576: Evaluate best-of-breed tools. Technology exploration.
- DLP-577: Evaluate best-of-breed tools. Technology exploration.
- DLP-639: Re-design camera geometry classes
- DLP-638: Refactor AFW R&D Code
- DLP-588: AFW R&D code refactored
- DLP-715: Fundamental centroid and shape measurements
- DLP-697: Single epoch CModel minimization
- DLP-696: Single epoch Sersic model fitting
- DLP-836: New logging for DM
- DLP-835: New xrootd client
- DLP-834: Automated Testbed for Qserv
![_static/graph_02C.00.png](/lsst-dm/dmtn-158/raw/main/_static/graph_02C.00.png)
Relationships between milestones in WBS 02C.00 and their immediate predecessors and successors. Ellipses correspond to milestones within this WBS element; rectangles to those in other elements. Blue milestones have been completed; orange milestones are overdue.
- WBS: 02C.00
- Level: 2
- Successors: DLP-556
- Due: 2014-09-02
- Completed: 2014-09-30
Warning
No description available
- WBS: 02C.00
- Level: 2
- Due: 2015-02-26
- Completed: 2015-03-06
Warning
No description available
- WBS: 02C.00
- Level: 1
- Successors: DM-NET-2
- Due: 2015-06-02
- Completed: 2015-06-01
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-400, DLP-554
- Successors: DLP-557, DLP-566
- Due: 2015-08-31
- Completed: 2015-09-01
Warning
No description available
- WBS: 02C.00
- Level: 1
- Due: 2015-10-01
- Completed: 2015-10-01
This is complete in. data/pmcs/201904-ME.xls.
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-364, DLP-389, DLP-556, DLP-486, DLP-103, DLP-100
- Successors: DLP-557
- Due: 2016-02-29
- Completed: 2016-07-12
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-694
- Due: 2016-05-31
- Completed: 2016-07-12
Warning
No description available
- WBS: 02C.00
- Level: 2
- Successors: S17S
- Due: 2016-07-05
- Completed: 2016-10-31
Complete with LCR-1788 June 2019.
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-556, DLP-566, DLP-579
- Successors: DLP-558
- Due: 2016-08-31
- Completed: 2016-08-31
Warning
No description available
- WBS: 02C.00
- Level: 3
- Successors: DLP-557
- Due: 2016-08-31
- Completed: 2017-12-01
Warning
No description available
- WBS: 02C.00
- Level: 2
- Successors: DLP-558
- Due: 2016-09-30
- Completed: 2016-10-31
Warning
No description available
- WBS: 02C.00
- Level: 2
- Successors: DLP-847, DLP-366, DLP-412, DLP-871
- Due: 2016-11-30
- Completed: 2016-11-30
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-850, DLP-405, DLP-541, DLP-871
- Successors: S17F
- Due: 2016-12-01
- Completed: 2016-12-01
Warning
No description available
- WBS: 02C.00
- Level: 2
- Due: 2017-02-28
- Completed: 2017-02-28
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: DMTC-0000-3000, S17F
- Successors: DLP-558
- Due: 2017-05-31
- Completed: 2017-05-31
approval of LCR-1494 in June 2019 allows this to be closed, LSE-400 :cite:`LSE-400` covers the items.
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: S17S
- Successors: DLP-61, DLP-538, DLP-736, DLP-152, DLP-473, DLP-472
- Due: 2017-05-31
- Completed: 2017-05-31
Warning
No description available
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-544, DLP-557, DLP-538
- Successors: DLP-551
- Due: 2017-08-31
- Completed: 2017-08-31
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-847, DLP-366, F17S
- Successors: DLP-368, DLP-459, DLP-458, DLP-457, DLP-442, DLP-433, DLP-207, DLP-205, DLP-222, DLP-473, DLP-725, DLP-344, DLP-352
- Due: 2017-11-30
- Completed: 2017-11-30
Warning
No description available
- WBS: 02C.00
- Level: 2
- Test specification: LDM-540 :cite:`LDM-540` v1.0 S3.1 (LSP-00)
- Predecessors: DM-SUIT-1, DM-SUIT-2, DM-SUIT-3, DM-SUIT-4, DM-DAX-1, DM-SQRE-1
- Successors: LDM-503-07
- Due: 2017-11-30
- Completed: 2018-05-30
This test demonstrates the deployment of the Portal and API Aspects of the LSST Science Platform (LSE-319 :cite:`LSE-319`, LDM-542 :cite:`LDM-542`, LDM-554 :cite:`LDM-554`) to serve all-sky precursor data, including catalogs totaling of order 50--100 billion rows, in a prototype LSST Data Access Center hosted in the LSST Data Facility at NCSA.
- WBS: 02C.00
- Level: 2
- Test specification: LDM-533 :cite:`LDM-533` v1.1 S3.1 (AG-00)
- Predecessors: DM-AP-1, DM-AP-2, DM-AP-3, DM-AP-4, DM-AP-5, DM-DAX-6
- Successors: LDM-503-05
- Due: 2017-11-30
- Completed: 2017-12-01
This test demonstrates the successful execution of a prototype Alert Generation science payload (LDM-148 :cite:`LDM-148`, LDM-151 :cite:`LDM-151`), processing data from precursor surveys at a relatively small scale using compute resources at the LSST Data Facility at NCSA.
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-368, DLP-412, DLP-459, DLP-458, DLP-457, DLP-207, DLP-205, DLP-222, DLP-725, DLP-352
- Successors: S19S
- Due: 2017-12-01
- Completed: 2017-12-01
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: DM-NCSA-27
- Successors: LSST-1190
- Due: 2017-12-29
- Completed: 2018-03-31
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: DM-NCSA-28, LSST-1160
- Successors: LSST-1200, LSST-1220
- Due: 2017-12-29
- Completed: 2018-03-30
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: DM-NCSA-29, LSST-1190
- Successors: F18S, LDM-503-06
- Due: 2017-12-29
- Completed: 2018-04-05
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: LSST-1190
- Successors: LSST-1580
- Due: 2017-12-29
- Completed: 2019-03-29
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-864
- Successors: DLP-33, DM-DRP-3, DM-DRP-5, DM-DRP-8, DM-DRP-9, DM-DRP-11, DM-DRP-17, DM-DRP-19, DM-DRP-38
- Due: 2018-05-31
- Completed: 2018-05-31
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: LSST-1200
- Successors: F19S, LDM-503-05, DM-AP-6, DM-AP-7, DM-AP-9
- Due: 2018-06-01
- Completed: 2018-06-01
Warning
No description available
- WBS: 02C.00
- Level: 1
- Predecessors: DLP-558
- Successors: DLP-552
- Due: 2018-08-31
- Completed: 2018-07-12
Warning
No description available
- WBS: 02C.00
- Level: 2
- Successors: DM-NCSA-11, DLP-464, DLP-466, DM-AP-8, DM-DRP-37, DM-DRP-29, DM-DAX-8, DM-DAX-10
- Due: 2018-11-30
- Completed: 2018-11-30
Warning
No description available
Warning
No description available
- WBS: 02C.00
- Level: 2
- Test specification: LDM-534 :cite:`LDM-534` v3.1 S3.1 (DRP-00)
- Predecessors: DM-NCSA-1, DM-NCSA-2, DM-NCSA-3, DM-AP-1, DM-DRP-1, DM-DRP-2
- Successors: DM-NCSA-4, LDM-503-07
- Due: 2019-02-28
- Completed: 2017-12-01
This test demonstrates the successful execution of a prototype Data Release Production science payload (LDM-148 :cite:`LDM-148`, LDM-151 :cite:`LDM-151`), processing data from precursor surveys at a relatively small scale using compute resources at the LSST Data Facility at NCSA.
- WBS: 02C.00
- Level: 2
- Test specification: LDM-538 :cite:`LDM-538` v1.0 S4.1 (RAS-00-00)
- Predecessors: DM-NCSA-4
- Successors: LDM-503-10, LDM-503-04b
- Due: 2019-02-28
- Completed: 2018-06-29
This test demonstrates that LSST data acquisition system can capture raw data from instrumentation and construct a well-formed image with proper headers.
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-112 :cite:`DMTR-112` :jirab:`DM-16072`
- Predecessors: LDM-503-01, LDM-503-02, DM-DRP-4
- Successors: LSST-1470, DLP-552, LDM-503-09
- Due: 2019-02-28
- Completed: 2019-01-17
This test demonstrates that the LSST Science Pipelines can be successfully used to load and perform basic processing of data from the LSST Camera test systems. In the process, it establishes that data is properly made available at the LSST Data Facility at NCSA, and is accessible through the LSST Science Platform.
LDM-503-04b: Test report: Aux Tel DAQ interface Integration Verification and Spectrograph Operations Rehearsal
- WBS: 02C.00
- Level: 2
- Test specification: LDM-538 :cite:`LDM-538` v1.0 S4.4 (RAS-00-20)
- Predecessors: DM-NCSA-27, DM-NCSA-5, DM-NCSA-6, DM-NCSA-7, LDM-503-04
- Successors: LDM-503-08
- Due: 2019-02-28
- Completed: 2018-06-29
This test demonstrates that the well-formed image generated in LDM-503-04 can be written to the permanent record of the survey.
- WBS: 02C.00
- Level: 2
- Successors: DLP-46, S20S, DM-SUIT-7, DM-SUIT-10
- Due: 2019-05-31
- Completed: 2019-05-31
Time-based milestone marking the completion of the Spring 2019 development cycle.
Warning
No description available
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-161 :cite:`DMTR-161` :jirab:`DM-19211`
- Predecessors: DM-DAX-2
- Successors: LDM-503-10b
- Due: 2019-07-29
- Completed: 2019-12-31 :jirab:`DM-19209`
This test demonstrates the successful integration of a single-sign-on federated authentication system, and a basic authorization system, with the three Aspects of the LSST Science Platform (Portal, Notebook, and API), with the API Aspect containing at least a TAP service.
- WBS: 02C.00
- Level: 1
- Predecessors: DM-NCSA-11, DLP-551, LDM-503-07
- Successors: LSST-1470, LDM-503-09
- Due: 2019-08-30
- Completed: 2019-08-30
This pipeline software release will precede LDM-503-12a. This will have all functionality required to process data from LSSTCam. It will not have the full functionality for data release processing.
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-102 :cite:`DMTR-102` :jirab:`DM-16073`
- Predecessors: A5860
- Successors: LDM-503-09
- Due: 2019-11-08
- Completed: 2019-07-15 :jirab:`DM-17118`
This test demonstrates the integration of the CCOB with the permanent record of the survey.
- WBS: 02C.00
- Level: 2
- Predecessors: F19S
- Successors: F20S, S20S, DM-STAFF
- Due: 2019-11-27
- Completed: 2019-11-29
Time-based milestone marking the completion of the Fall 2019 development cycle.
- WBS: 02C.00
- Level: 2
- Predecessors: F19F
- Successors: LDM-503-13
- Due: 2019-11-27
- Completed: 2019-11-29
DM Management evaluate current DM staffing against project schedule and budget. If there is a shortfall through mid-2022 (the “ops gap”), this is the point at which we need to fill it.
- WBS: 02C.00
- Level: 2
- Predecessors: S19S, S19F, F19F
- Successors: S21S, S20F
- Due: 2019-12-02
- Completed: 2019-12-02
Warning
No description available
- WBS: 02C.00
- Level: 1
- Successors: COMC-1564, COMC-0620-2090
- Due: 2020-05-13
- Completed: 2020-02-28
This milestone represents the availability of the base center in Las Serena. This includes DM staging machines, the commissioning cluster. It also includes the Chilean Data Access center machines. The later will only be deployed after the US DAC is up.
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-171 :cite:`DMTR-171` :jirab:`DM-16074`
- Predecessors: DM-NCSA-10, DM-NCSA-11, LSST-1200, T&SC-6500-9000, T&SC-7900-2430
- Successors: LDM-503-10, LDM-503-11a
- Due: 2020-05-27
- Completed: 2020-06-30 :jirab:`DM-17119`
This milestone records successful transfer of an image equivalent to one raft from the DAQ at the summit to reliable storage in the LSST Data Facility at NCSA, from where it will be made available for scientific evaluation through the LSST Science Platform.
- WBS: 02C.00
- Level: 2
- Predecessors: S20S
- Successors: F20S, S21S, LDM-503-10b, DM-AP-18
- Due: 2020-05-29
- Completed: 2020-05-29
Time-based milestone marking the completion of the Spring 2020 development cycle.
- WBS: 02C.00
- Level: 2
- Test specification: LDM-533 :cite:`LDM-533` v2.0 SS 4.7--4.9 (test cases LVV-T216, LVV-T217, LVV-T218)
- Predecessors: DM-NCSA-9, F18S, LDM-503-03, DM-AP-18
- Successors: LDM-503-09
- Due: 2020-05-29
- Completed: 2018-07-17
This test demonstrates that a full-LSST-scale (10,000 messages every 39 seconds) alert stream can be distributed to end users. It further shows that simple filters based on alert contents can be applied to that stream.
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-182 :cite:`DMTR-182` :jirab:`DM-16194`
- Predecessors: CAMM8040, CAMM8300, S20F, LDM-503-10a
- Successors: LSST-1580
- Due: 2020-05-29
- Completed: 2020-04-22 :jirab:`DM-17123`
Demonstrate the ability to transfer data from the CCOB with 21 rafts from SLAC and ingested at NCSA and make available through an instance of the LSP.
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-111 :cite:`DMTR-111` :jirab:`DM-16076`
- Predecessors: DM-AP-2, DM-AP-3, DM-AP-6, DM-AP-7, DM-AP-9, DM-DRP-3, DM-DRP-5, DM-DRP-7, DM-DRP-16, DM-DRP-17, DM-DRP-32, DM-DRP-38
- Successors: LDM-503-09, LDM-503-11
- Due: 2020-05-29
- Completed: 2019-04-12 :jirab:`DM-17121`
This milestone describes a software release of the LSST Science Pipelines in support of activities in late 2018 and early 2019. The contents of the release are described in LDM-564 :cite:`LDM-564`. The release will be accompanied by a characterization report.
- WBS: 02C.00
- Level: 2
- Predecessors: S20F, F19F
- Successors: F21S, F20F, DM-AP-10, DM-DRP-22
- Due: 2020-06-01
- Completed: 2020-06-01
Time-based milestone marking the start of the Fall 2020 development cycle.
- WBS: 02C.00
- Level: 2
- Predecessors: F20S, DM-DRP-11, DLP-837
- Successors: DLP-465, DLP-468, DLP-467, F21S, S21S, LDM-503-11, DM-DRP-30, DM-DRP-34, DM-DAX-12, DM-DAX-14, DM-SQRE-6, DM-SQRE-7
- Due: 2020-11-30
- Completed: 2020-11-30
Time-based milestone marking the completion of the Fall 2020 development cycle.
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-121 :cite:`DMTR-121` :jirab:`DM-16455`
- Predecessors: CAMM8300, DM-NCSA-13, DM-NCSA-14, DM-NCSA-15, DM-NET-2, DM-NET-3, DM-NET-6, LDM-503-04b, DM-DRP-6
- Successors: LDM-503-10, LDM-503-11
- Due: 2020-11-30
- Completed: 2019-12-31 :jirab:`DM-17131`
This test demonstrates data acquisition from the Auxiliary Telescope spectrograph, transmission of all image files with associated metadata to NCSA for screening, and then further processing if needed.
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-181 :cite:`DMTR-181` :jirab:`DM-16193`
- Predecessors: IT-725-M, LDM-503-04, LDM-503-06, LDM-503-08
- Successors: LDM-503-11
- Due: 2020-11-30
- Completed: 2020-06-22 :jirab:`DM-17122`
Test of the extended data acquisition (DAQ) network in Chile from the Summit to the Base Data Center.
- WBS: 02C.00
- Level: 2
- Test specification: Undefined :jirab:`DM-16196`
- Predecessors: DM-NCSA-16, DM-NCSA-20, DM-NCSA-22, LDM-503-06, DM-SUIT-10
- Successors: LDM-503-12
- Due: 2020-11-30
- Completed: 2020-12-31 :jirab:`DM-17125`
Demonstrate that all DM functionality required to support ComCam operations has been delivered.
- WBS: 02C.00
- Level: 2
- Test specification: LDM-643 :cite:`LDM-643` :jirab:`DM-16075`
- Predecessors: DM-NCSA-16, A4680, A4860, DLP-552, S21S, LDM-503-05, LDM-503-07, LDM-503-08b, LDM-503-09a, DM-SUIT-5, DM-DAX-2, DM-DAX-5, DM-SQRE-2, A2370
- Successors: LDM-503-11
- Due: 2020-12-01
- Completed: 2019-10-07 :jirab:`DM-17120`
This milestone represents the completion of a multi-day exercise in which (simulated) observations are performed and data is processed in as close to an operational mode as is possible at this stage in construction. In particular, it will demonstrate transfer, archiving and ingestion of raw data; offline processing of calibration and science data; and curation of the resultant data products.
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-192 :cite:`DMTR-192` :jirab:`DM-16197`
- Predecessors: S21S, DM-AP-8, DM-DRP-9, DM-DRP-14, DM-DRP-15, DM-DRP-18, DM-DRP-19
- Successors: LDM-503-13a
- Due: 2020-12-01
- Completed: 2020-11-30 :jirab:`DM-17126`
This milestone describes a software release of the LSST Science Pipelines in support of activities in late 2019 and early 2020. The contents of the release are described in LDM-564 :cite:`LDM-564`. The release will be accompanied by a characterization report.
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-301 :cite:`DMTR-301` :jirab:`DM-26340`
- Predecessors: S21S
- Successors: LDM-503-12a
- Due: 2020-12-01
- Completed: 2021-09-30 :jirab:`DM-26349`
The Rubin Science Platform is ready to support Data Preview 0.1 as deployed on the IDF. The RSP capabilities are largely those demonstrated under previous milestones, but ported to the IDF and with deployment and authentication/authorization infrastructure improvements that support the scale of DP0.1 usage. The Notebook Aspect provides access to the Rubin Science Pipelines stack and to data exposed in a cloud-deployed Gen3 Butler repository; the API Aspect provides TAP queries against a Qserv deployment of catalog tables, but not image metadata; and the Portal Aspect provides a UI for visual and ADQL construction of queries against those tables. Image and image metadata access services in the API and Portal Aspects are not included.
- WBS: 02C.00
- Level: 2
- Test specification: LDM-643 :cite:`LDM-643` :jirab:`DM-16195`
- Predecessors: DM-NCSA-16, DLP-468, DLP-467, DM-NET-4, F20F, LDM-503-08, LDM-503-09, LDM-503-10, LDM-503-09a
- Successors: LDM-503-12
- Due: 2021-01-04
- Completed: 2021-09-30 :jirab:`DM-17124`
Template generation, including code required to build templates in both Data Release and Alert Production science payloads, can now product templates which are corrected for the effects of Differential Chromatic Refraction (DCR), as described in LDM-151 :cite:`LDM-151` §6.18. Further, noise in image differences can be “decorrelated”, as described in LDM-151 :cite:`LDM-151` §6.19.1. Both of these represents initial capabilities, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithms being used is expected.
- WBS: 02C.00
- Level: 2
- Predecessors: S20S, S20F, F20F
- Successors: S22S, S21F, LDM-503-09, LDM-503-11b, LDM-503-14a
- Due: 2021-04-30
- Completed: 2021-04-30
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: S21S
- Successors: DM2, DM9, F21S, S22S, LDM-503-13a, DM-IT-FIB, DM-DRP-28, DM-DAX-13
- Due: 2021-05-31
- Completed: 2021-05-31
Time-based milestone marking the completion of the Spring 2021 development cycle.
- WBS: 02C.00
- Level: 2
- Predecessors: S21F
- Successors: COMC-060200-20100
- Due: 2021-05-31
- Completed: 2021-10-29
Camera fibers ready deployed from the Computer Room to the top of the TMA.
- WBS: 02C.00
- Level: 2
- Predecessors: F20S, S21F, F20F
- Successors: F21F, DM-DRP-23
- Due: 2021-06-01
- Completed: 2021-06-01
Warning
No description available
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-302 :cite:`DMTR-302` :jirab:`DM-16200`
- Predecessors: S21F, LDM-503-11b, DM-AP-11, DM-AP-13, DM-DRP-22, DM-DRP-26, DM-DRP-28, DM-DRP-30, DM-DRP-34
- Successors: LDM-503-13, LDM-503-14, LDM-503-15a
- Due: 2021-08-31
- Completed: 2021-07-31 :jirab:`DM-17129`
This milestone describes a software release of the LSST Science Pipelines in support of activities in late 2020 and early 2021. The contents of the release are described in LDM-564 :cite:`LDM-564`. The release will be accompanied by a characterization report.
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-271 :cite:`DMTR-271` :jirab:`DM-27336`
- Predecessors: DM-DAX-13
- Successors: F21F
- Due: 2021-09-30
- Completed: 2022-05-31 :jirab:`DM-27337`
Show parity of Butler Gen3 with Butler Gen2 systems. We should be able to run processing pipelines with Gen3 which previously ran on Gen2. Demonstrate the ability to write new pipelines using the framework. Framework should be ready to support Preops processing, specifically DP0.2 (RTN-001 :cite:`RTN-001`).
- WBS: 02C.00
- Level: 2
- Predecessors: F21S, LDM-GEN3
- Successors: S22S, LDM-503-12
- Due: 2021-11-30
- Completed: 2021-11-30
Time-based milestone marking the completion of the Fall 2021 development cycle.
- WBS: 02C.00
- Level: 2
- Predecessors: S21S, S21F, F21F
- Successors: DM-PORTAL, DM-CLOUD
- Due: 2021-12-01
- Completed: 2021-12-01
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: S22S
- Successors: LSST-1580
- Due: 2021-12-01
- Completed: 2022-01-31
Warning
No description available
- WBS: 02C.00
- Level: 2
- Predecessors: S22S
- Successors: LSST-1580
- Due: 2021-12-01
- Completed: 2022-01-31
Warning
No description available
- WBS: 02C.00
- Level: 2
- Successors: LSST-1590, DM11, LDM-503-15a
- Due: 2022-05-05
- Completed: 2022-05-31
Time-based milestone marking the completion of the Spring 2022 development cycle.
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-231 :cite:`DMTR-231` :jirab:`DM-17136`
- Predecessors: S22F, LDM-503-13a, DM-AP-12, DM-DRP-27
- Successors: LDM-503-17a
- Due: 2022-05-05
- Completed: 2022-02-28 :jirab:`DM-17137`
This milestone describes a software release of the LSST Science Pipelines in support of activities in late 2021 and early 2022. The contents of the release are described in LDM-564 :cite:`LDM-564`. The release will be accompanied by a characterization report.
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-381 :cite:`DMTR-381` :jirab:`DM-30112`
- Successors: LDM-503-17a, LDM-503-RSPb
- Due: 2022-09-30
- Completed: 2023-01-31 :jirab:`DM-30113`
The Rubin Science Platform is ready to support Data Preview 0.2 as deployed on the IDF. The RSP serves an end-to-end Rubin-Gen3-processed dataset with a substantial set of image and SDM-ified catalog data products. Beyond the capabilities provided under LDM-503-14a, this deployment provides: initial IVOA-oriented image metadata and image services in the API Aspect, specifically an ObsTAP service and a basic SODA-compatible image cutout service; Portal Aspect support for accessing these services and browsing images from the released dataset; and access to a User File Workspace from all three Aspects.
LDM-503-EFDa: Engineering Facility Database at the summit capturing and enabling access to all telemetry with M1/M3 active
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-291 :cite:`DMTR-291` :jirab:`DM-26342`
- Predecessors: COMC-0030
- Successors: LDM-503-12a, LDM-503-EFDb
- Due: 2023-06-16
- Completed: 2021-09-30 :jirab:`DM-26348`
An instance of the Engineering and Facility Database at the summit capturing and enabling access to all telemetry, including from an active M1M3. This may be distinct from the Auxiliary Telescope EFD instance. Demonstrate the ability to run for five days, allowing data retrieval and plotting via notebooks.
LDM-503-EFDb: EFD/telemetry data replicated at the LDF, stored in InfluxDB. aggregated into parquet files
- WBS: 02C.00
- Level: 2
- Test specification: Undefined :jirab:`DM-26344`
- Predecessors: LDM-503-EFDa, COMC-0030
- Successors: LSST-1520
- Due: 2023-06-16
- Completion pending :jirab:`DM-26347`
Demonstrate that EFD data from the Summit appears at a Data Facility. Show that the Parquet files generated contain all low frequency EFD values and summaries of high frequency values.
- WBS: 02C.00
- Level: 4
- Test specification: Undefined :jirab:`DM-38758`
- Successors: DM-READY
- Due: 2024-01-11
- Completion pending :jirab:`DM-38759`
This milestone represents the point at which Qserv completes construction and enters full operation and maintenance. A testplan should be executed showing the requirements are verified.
- WBS: 02C.00
- Level: Undefined
- Successors: LDM-503-NET
- Due: 2024-02-16
- Completed: 2023-01-31
Warning
No description available
- WBS: 02C.00
- Level: 4
- Test specification: LDM-732 :cite:`LDM-732` :jirab:`IT-3681`
- Predecessors: NET-neutral
- Successors: LDM-503-14, COMC-0620-2065
- Due: 2024-04-15
- Completion pending
Network verified.
- WBS: 02C.00
- Level: 2
- Test specification: Undefined :jirab:`DM-16201`
- Predecessors: LSST-1470, DM-STAFF, LDM-503-13a
- Successors: LDM-503-14, LDM-503-15
- Due: 2024-04-30
- Completed: 2023-02-28 :jirab:`DM-17130`
This milestone builds upon LDM-503-12, but with its scope extended beyond procedures which are necessary in commissioning to cover the operational era.
- WBS: 02C.00
- Level: 2
- Test specification: Undefined :jirab:`DM-32560`
- Predecessors: COMC-0240
- Successors: LDM-503-17a
- Due: 2024-05-01
- Completed: 2023-08-31 :jirab:`DM-32561`
This milestone describes a software release of the LSST Science Pipelines in support of activities in late 2023 and early 2023. The contents of the release are described in LDM-564 :cite:`LDM-564`. The release will be accompanied by a characterization report.
- WBS: 02C.00
- Level: 2
- Test specification: Undefined :jirab:`DM-17134`
- Predecessors: LDM-503-13
- Successors: LDM-503-16
- Due: 2024-07-23
- Completed: 2023-08-31 :jirab:`DM-17135`
This milestone builds upon LDM-503-13, and will demonstrate the production of a data release under simulated operational conditions using data from science verification activities.
- WBS: 02C.00
- Level: 2
- Test specification: Undefined :jirab:`DM-16198`
- Predecessors: F21F, LDM-503-11, LDM-503-11a, DM-SQRE-3
- Successors: LDM-503-14, SITCOM-114
- Due: 2024-11-01
- Completion pending :jirab:`DM-17127`
This milestone builds upon LDM-503-11, and serves to demonstrate that all necessary procedures and workflows are in place to support commissioning activities.
- WBS: 02C.00
- Level: 2
- Test specification: Undefined :jirab:`DM-17132`
- Predecessors: LDM-503-12, LDM-503-13, LDM-503-13a, LDM-503-NET, LDM-503-19a, DM-SQRE-4
- Successors: COMC-060200-20960
- Due: 2024-11-01
- Completion pending :jirab:`DM-17133`
This milestone represents the point at which all code and/or services which are supplied by DM in support of science verification will be tested and demonstrated to meet their requirements.
- WBS: 02C.00
- Level: 2
- Test specification: Undefined :jirab:`DM-17138`
- Predecessors: LSST-1520, LDM-503-15, SITCOM-130
- Successors: DM9, LDM-503-17, SITCOM-119
- Due: 2024-11-01
- Completion pending :jirab:`DM-17139`
This milestone builds upon LDM-503-15 to demonstrate the production of prompt products over several nights.
- WBS: 02C.00
- Level: 2
- Test specification: Undefined :jirab:`DM-16199`
- Predecessors: LSST-1520, CAMM8090, LDM-503-14a, LDM-503-EFDa, COMC-0030
- Successors: DM1, LDM-503-EFDc, DM-AP-15, DM-AP-17, SUMMIT-3077, SITCOM-126
- Due: 2024-11-01
- Completion pending :jirab:`DM-17128`
Demonstrate that all DM functionality required to support operations with the full LSST Camera has been delivered.
- WBS: 02C.00
- Level: 2
- Test specification: Undefined :jirab:`DM-26345`
- Predecessors: LDM-503-12a
- Successors: LDM-503-17a
- Due: 2024-11-01
- Completion pending :jirab:`DM-26346`
Demonstrate that engineering data for a specific observation time can be retrieved via TAP on the Science Platform or directly to a TAP tool like Topcat. Test DMS-REQ-0102 (Priority 1a) to permanently archive metadata from OCS and make available to rights holders. Also test DMS-REQ-0358 (Priority 1a), demonstrating support of simultaneous queries.
- WBS: 02C.00
- Level: 4
- Predecessors: LSST-1520
- Successors: LDM-503-17
- Due: 2024-11-01
- Completed: 2023-09-29
Warning
No description available
- WBS: 02C.00
- Level: 2
- Test specification: Undefined :jirab:`DM-38727`
- Predecessors: LSST-1520
- Successors: LSST-1580, LDM-503-14, SITCOM-114
- Due: 2024-11-01
- Completion pending :jirab:`DM-38728`
This milestone represents the point at which all code and/or services needed for commissioning (i.e. 1a requirements) are verified.
- WBS: 02C.00
- Level: 1
- Successors: DM2, COMC-1664
- Due: 2024-12-09
- Completion pending
This milestone represents the availability of an archive center to host LSST DR1 data. This includes an science platform interface with the implied services for Data Access, a portal and Notebooks.
- WBS: 02C.00
- Level: 2
- Test specification: Undefined :jirab:`DM-17140`
- Predecessors: DM2, DM11, DM9, LDM-503-16, RSP-1200, COMC-0620-9000
- Successors: LSST-1580
- Due: 2024-12-09
- Completion pending :jirab:`DM-17141`
This milestone builds upon LDM-503-16 to demonstrate successful operation of all aspects of the DM subsystem under simulated operational conditions.
- WBS: 02C.00
- Level: 2
- Test specification: Undefined :jirab:`DM-30116`
- Predecessors: LSST-1540, LDM-503-RSPa
- Successors: LDM-503-17a
- Due: 2024-12-09
- Completion pending :jirab:`DM-30117`
The Rubin Science Platform is ready to support Science Verification activities in the final phase of Rubin Observatory commissioning. In additional to the capabilities demonstrated in Milestone-2 (LDM-503-RSPa), the RSP will be scalable to the user load required to support Science Verification; provide access to a regularly updating stream of newly-acquired LSSTCam data; provide access to next-to-data computing and user batch computing to support intensive data analysis; provide access to a User Database Workspace; provide a means for integrating with a TBD focal-plane-scale visualization tool; provide capabilities in all three Aspects for following links between related datasets and exploiting provenance information; provide access to the EFD for recently acquired data, extending the capability demonstrated for LDM-503-EFDc; and provide substantial user-facing documentation, with links between the data and documentation.
- WBS: 02C.00
- Level: 2
- Test specification: Undefined :jirab:`DM-17142`
- Predecessors: LDM-503-15a, LDM-503-EFDc, LDM-503-RSPa, LDM-503-RSPb, LDM-503-16a, DM-DAX-9, COMC-0654-1070
- Successors: LSST-1580, DM-READY, LDM-503-19, DM-AP-14, DM-AP-16
- Due: 2025-02-27
- Completion pending :jirab:`DM-17143`
This milestone describes the final Science Pipelines release from the DM Construction Project. The contents of the release are described in LDM-564 :cite:`LDM-564`. The release will be accompanied by a characterization report.
- WBS: 02C.00
- Level: 4
- Predecessors: LDM-503-17a, LDM-503-19, LDM-503-18q
- Successors: SITCOM-130
- Due: 2025-02-27
- Completion pending
Warning
No description available
- WBS: 02C.00
- Level: 4
- Test specification: Undefined :jirab:`DM-38748`
- Predecessors: LDM-503-17a
- Successors: DM-READY, SITCOM-130
- Due: 2025-02-27
- Completion pending :jirab:`DM-38749`
This milestone represents the point at which all code and/or services needed for operations (i.e. 1a and 1b requirements) are verified.
![_static/graph_02C.03.png](/lsst-dm/dmtn-158/raw/main/_static/graph_02C.03.png)
Relationships between milestones in WBS 02C.03 and their immediate predecessors and successors. Ellipses correspond to milestones within this WBS element; rectangles to those in other elements. Blue milestones have been completed; orange milestones are overdue.
- WBS: 02C.03.01
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-13
Warning
No description available
- WBS: 02C.03.05
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-13
Warning
No description available
- WBS: 02C.03.01
- Level: 3
- Due: 2014-12-10
- Completed: 2014-12-10
Warning
No description available
- WBS: 02C.03.08
- Level: 3
- Due: 2015-02-24
- Completed: 2015-02-24
Warning
No description available
- WBS: 02C.03.04
- Level: 3
- Successors: DLP-276
- Due: 2015-10-29
- Completed: 2016-04-08
Warning
No description available
- WBS: 02C.03.04
- Level: 3
- Predecessors: DLP-275
- Due: 2016-01-22
- Completed: 2016-07-12
Warning
No description available
- WBS: 02C.03
- Level: 3
- Successors: LDM-503-02, LDM-503-03, DM-AP-10
- Due: 2017-08-31
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.03
- Level: 3
- Successors: LDM-503-03, LDM-503-09a, DM-AP-11
- Due: 2017-08-31
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.03
- Level: 3
- Successors: LDM-503-03, LDM-503-09a, DM-AP-13
- Due: 2017-08-31
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.03
- Level: 3
- Successors: LDM-503-03
- Due: 2017-08-31
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.03
- Level: 3
- Successors: LDM-503-03
- Due: 2017-08-31
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.03
- Level: 3
- Predecessors: F18S, DM-DRP-4
- Successors: LDM-503-09a
- Due: 2018-06-29
- Completed: 2018-06-29
Warning
No description available
- WBS: 02C.03
- Level: 3
- Predecessors: F18S
- Successors: LDM-503-09a, DM-DRP-17, DM-DRP-21
- Due: 2018-07-20
- Completed: 2018-11-29
Warning
No description available
DM-AP-8: Advanced ISR, including ghost and linear feature masking, correction for the Brighter-Fatter effect and compensation for pixel response non-uniformity.
- WBS: 02C.03
- Level: 3
- Predecessors: F18F
- Successors: LDM-503-11b
- Due: 2019-01-04
- Completed: 2019-01-17
Warning
No description available
DM-AP-11: Difference imaging includes noise decorrelation and correction for differential chromatic refraction.
- WBS: 02C.03
- Level: 3
- Predecessors: DM-AP-2
- Successors: LDM-503-13a, DM-AP-12, DM-DRP-28
- Due: 2019-11-27
- Completed: 2019-10-01
Template generation, including code required to build templates in both Data Release and Alert Production science payloads, can now product templates which are corrected for the effects of Differential Chromatic Refraction (DCR), as described in LDM-151 :cite:`LDM-151` §6.18. Further, noise in image differences can be “decorrelated”, as described in LDM-151 :cite:`LDM-151` §6.19.1. Both of these represents initial capabilities, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithms being used is expected.
- WBS: 02C.03
- Level: 3
- Predecessors: DM-NCSA-9, F18S, DM-AP-18
- Successors: LDM-503-09a, DM-AP-14
- Due: 2020-05-29
- Completed: 2018-07-31
Warning
No description available
- WBS: 02C.03
- Level: 3
- Predecessors: S20F
- Successors: LDM-503-05, DM-AP-6
- Due: 2020-05-29
- Completed: 2020-05-29
The AP Pipeline is now capable of generating per-DIASource alert packets, which comply with the current version of the LSST alert schema. This milestone only covers packet generation; success involves only those serialized alerts being e.g. written to disk, and does not imply that an alert transport system is available.
- WBS: 02C.03
- Level: 3
- Predecessors: F20S, DM-AP-1
- Successors: LSST-1580
- Due: 2020-06-01
- Completed: 2023-05-31
The Single Frame Processing system is now substantially complete and provides all functionality described in LDM-151 :cite:`LDM-151` §3.1. It supports all expected interfaces, data-flows, and products, but the details of the algorithms are expected to undergo continued refinement.
- WBS: 02C.03
- Level: 3
- Predecessors: DM-AP-11
- Successors: LDM-503-15a
- Due: 2021-08-31
- Completed: 2023-05-31
The Alert Generation science payload is now agnostic to the PSF of the template, as described in LDM-151 :cite:`LDM-151` §3.2.4. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
- WBS: 02C.03
- Level: 3
- Predecessors: DM-AP-3
- Successors: LDM-503-13a
- Due: 2021-08-31
- Completed: 2021-10-29
The Alert Generation science payload now provides the capability to fit a trailed point source model to detections made on difference images, as described in LDM-151 :cite:`LDM-151` §3.2.4. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
- WBS: 02C.03
- Level: 3
- Predecessors: LDM-503-12a
- Successors: DM16, DM11, DM-AP-16
- Due: 2024-11-01
- Completion pending
The Alert Distribution system (LDM-151 :cite:`LDM-151` §3.3) is now available for deployment at the LSST Data Facility. The system is substantially complete, and supports all expected interfaces, data-flows, and products, but the details of the algorithms may undergo continued refinement.
- WBS: 02C.03
- Level: 3
- Predecessors: LDM-503-12a, SITCOM-122
- Successors: DM-DRP-36
- Due: 2024-11-01
- Completion pending
All of the algorithmic components which comprise the Solar System Processing (SSP) pipeline, as described in LDM-151 :cite:`LDM-151` §§6.25–6.28, are available for integration into science payloads. These components must provide realistic interfaces, data-flows and products, but it is expected that the details of the algorithms will undergo continued refinement.
- WBS: 02C.03
- Level: 3
- Predecessors: LDM-503-17a, DM-AP-6
- Successors: LSST-1580
- Due: 2025-02-27
- Completion pending
The Alert Filtering Service (LDM-151 :cite:`LDM-151` §3.3.4; LSE-163 :cite:`LSE-163` §3.5.2) can now be deployed as part of a prototype Alert Distribution system (LDM-151 :cite:`LDM-151` §3.3). This service is substantially complete, and supports all expected interfaces, data-flows, and products, but may not yet provide the complete set of filtering capabilities and/or may not perform at the level required to distribute the full LSST alert stream.
- WBS: 02C.03
- Level: 3
- Predecessors: LDM-503-17a, DM-AP-15, COMC-0240
- Successors: LSST-1580
- Due: 2025-02-27
- Completion pending
The Alert Production system (comprising Single Frame Processing, LDM-151 :cite:`LDM-151` §3.1; Alert Generation, LDM-151 :cite:`LDM-151` §3.3; and Precovery and Forced Photometry, LDM-151 :cite:`LDM-151` §3.4) is now available for deployment at the LSST Data Facility. The system is substantially complete, and supports all expected interfaces, data-flows and products, but the details of the algorithms may undergo continued refinement.
![_static/graph_02C.04.png](/lsst-dm/dmtn-158/raw/main/_static/graph_02C.04.png)
Relationships between milestones in WBS 02C.04 and their immediate predecessors and successors. Ellipses correspond to milestones within this WBS element; rectangles to those in other elements. Blue milestones have been completed; orange milestones are overdue.
- WBS: 02C.04.01
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
- WBS: 02C.04.06
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2015-12-04
Warning
No description available
- WBS: 02C.04.06
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
- WBS: 02C.04.06
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
- WBS: 02C.04.06
- Level: 3
- Due: 2014-09-12
- Completed: 2014-09-12
Warning
No description available
- WBS: 02C.04.06
- Level: 3
- Due: 2014-09-12
- Completed: 2014-09-12
Warning
No description available
- WBS: 02C.04.04
- Level: 3
- Due: 2015-08-31
- Completed: 2015-08-31
Warning
No description available
- WBS: 02C.04.04
- Level: 3
- Due: 2015-08-31
- Completed: 2015-08-31
Warning
No description available
- WBS: 02C.04.05
- Level: 3
- Due: 2015-11-24
- Completed: 2016-04-11
Warning
No description available
- WBS: 02C.04.01
- Level: 3
- Due: 2015-11-24
- Completed: 2017-05-09
Warning
No description available
- WBS: 02C.04.06
- Level: 3
- Due: 2015-12-04
- Completed: 2016-05-31
Warning
No description available
- WBS: 02C.04.01
- Level: 3
- Due: 2015-12-29
- Completed: 2016-12-07
Warning
No description available
- WBS: 02C.04.05
- Level: 3
- Successors: DLP-566
- Due: 2016-02-29
- Completed: 2016-04-11
Warning
No description available
- WBS: 02C.04.05
- Level: 3
- Successors: DLP-566
- Due: 2016-02-29
- Completed: 2016-04-11
Warning
No description available
- WBS: 02C.04.05
- Level: 3
- Successors: DLP-566
- Due: 2016-02-29
- Completed: 2016-04-11
Warning
No description available
- WBS: 02C.04.02
- Level: 3
- Successors: DMTC-0000-0020
- Due: 2016-05-31
- Completed: 2016-05-31
Warning
No description available
DM-DRP-1: HSC merger complete: all functionality deployed for the most recent HSC data release processing is now available within the LSST stack.
- WBS: 02C.04
- Level: 3
- Successors: DM-NCSA-1, DM-NCSA-16, LDM-503-02
- Due: 2017-05-31
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.04
- Level: 3
- Successors: LDM-503-07, DM-AP-7, DM-DRP-20
- Due: 2017-05-31
- Completed: 2017-12-01
Warning
No description available
- WBS: 02C.04.01
- Level: 3
- Predecessors: DMTC-0000-3000, S17F
- Successors: F17S
- Due: 2017-05-31
- Completed: 2016-12-19
Warning
No description available
- WBS: 02C.04.04
- Level: 3
- Predecessors: S17F
- Due: 2017-05-31
- Completed: 2016-12-19
Warning
No description available
- WBS: 02C.04
- Level: 3
- Successors: LDM-503-08
- Due: 2017-08-31
- Completed: 2018-01-31
Warning
No description available
- WBS: 02C.04
- Level: 3
- Successors: LDM-503-11b
- Due: 2017-11-30
- Completed: 2017-12-01
Warning
No description available
- WBS: 02C.04
- Level: 3
- Successors: LDM-503-11b
- Due: 2017-11-30
- Completed: 2017-12-01
Warning
No description available
- WBS: 02C.04
- Level: 3
- Successors: LDM-503-09a
- Due: 2018-01-31
- Completed: 2018-05-31
Warning
No description available
- WBS: 02C.04
- Level: 3
- Successors: LDM-503-09a
- Due: 2018-03-30
- Completed: 2018-10-31
Warning
No description available
- WBS: 02C.04
- Level: 3
- Predecessors: S18F
- Successors: LDM-503-09a, DM-DRP-37
- Due: 2018-06-29
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.04
- Level: 3
- Predecessors: S18F
- Successors: LDM-503-09a
- Due: 2018-06-29
- Completed: 2018-06-29
Warning
No description available
- WBS: 02C.04
- Level: 3
- Predecessors: S18F
- Successors: LDM-503-09a
- Due: 2018-06-29
- Completed: 2018-06-29
Warning
No description available
- WBS: 02C.04
- Level: 3
- Successors: LDM-503-09a, T&SC-2100-2252
- Due: 2018-07-12
- Completed: 2018-07-05
Warning
No description available
- WBS: 02C.04
- Level: 3
- Predecessors: S18F, DM-AP-9
- Successors: LDM-503-09a
- Due: 2018-07-20
- Completed: 2018-11-29
Warning
No description available
- WBS: 02C.04
- Level: 3
- Predecessors: S18F
- Successors: LDM-503-11b, DM-DRP-23
- Due: 2018-10-15
- Completed: 2019-03-25
Warning
No description available
- WBS: 02C.04
- Level: 3
- Predecessors: S18F
- Successors: LDM-503-11b
- Due: 2018-11-29
- Completed: 2018-12-13
Warning
No description available
- WBS: 02C.04
- Level: 3
- Predecessors: F18F, DM-DRP-3
- Successors: LSST-1580
- Due: 2018-11-30
- Completion pending
The Data Release Production science payload now includes code for generating final estimates of the sky background and artifact masks, as described in LDM-151 :cite:`LDM-151` §5.2.2. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
- WBS: 02C.04
- Level: 3
- Predecessors: F18F
- Successors: LSST-1580
- Due: 2018-11-30
- Completed: 2022-12-31
The Data Release Production science payload now includes the capability of fitting moving a moving point source model that includes parallax and proper motion as free parameters to all objects, as described in LDM-151 :cite:`LDM-151` §6.7.2. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithms being used is expected.
- WBS: 02C.04
- Level: 3
- Predecessors: DM-NCSA-3, DM-DAX-5
- Successors: LDM-503-02
- Due: 2019-02-28
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.04
- Level: 3
- Predecessors: S18F
- Successors: F20F, DM-DAX-5
- Due: 2019-02-28
- Completed: 2019-12-31
The Data Release Production science payload now generates results which are compliant with the LSST Science Data Model, and which are suitable for database ingest.
- WBS: 02C.04
- Level: 3
- Predecessors: DM-DRP-4
- Successors: LSST-1580, SITCOM-120
- Due: 2019-11-27
- Completed: 2021-07-29
The Calibration Products Production science payload is now capable of generating all calibration products which are required to enter commissioning.
- WBS: 02C.04
- Level: 3
- Predecessors: S18F, COMC-060200-10000
- Successors: LSST-1580
- Due: 2020-01-21
- Completed: 2021-07-31
The Calibration Products Production science payload is now capable of generating those products which are required to calibrate the Auxiliary Telescope. This represent an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithms being used is expected.
- WBS: 02C.04
- Level: 3
- Predecessors: F20S
- Successors: LDM-503-13a
- Due: 2020-06-01
- Completed: 2021-03-31
The Data Release Production science payload is now capable of generating templates for use in image differencing, as described in LDM-151 :cite:`LDM-151` §§5.2.3 & 5.2.4. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
- WBS: 02C.04
- Level: 3
- Predecessors: DM-DAX-8
- Successors: LSST-1580
- Due: 2020-11-30
- Completed: 2020-06-30
Warning
No description available
- WBS: 02C.04
- Level: 3
- Predecessors: DM-DAX-8
- Successors: LSST-1580, DM-DRP-15
- Due: 2020-11-30
- Completed: 2023-02-28
The Data Release Production science payload now includes code for estimating the PSF over the full focal plane, as described in LDM-151 :cite:`LDM-151` §6.11.3. This does not require that the PSF model be “physically motivated” (ie, decomposed into atmospheric and optical components). Further, this represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-15: All varieties of coadd required for object detection and characterization are now produced during normal pipeline operation (although not necessarily at the ultimately required level of fidelity).
- WBS: 02C.04
- Level: 3
- Predecessors: DM-DRP-13
- Successors: LDM-503-11b
- Due: 2020-11-30
- Completed: 2018-11-30
Warning
No description available
- WBS: 02C.04
- Level: 3
- Predecessors: DM-AP-9, DM-DAX-8
- Successors: LSST-1580
- Due: 2020-11-30
- Completed: 2021-10-29
The Data Release Production science payload now includes an integrated image characterization pipeline, as described in LDM-151 :cite:`LDM-151` §5.1, including iterative refinement of the image characterization. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-30: Forced photometry is now performed on individual processed visit images during data releases.
- WBS: 02C.04
- Level: 3
- Predecessors: F20F
- Successors: LDM-503-13a
- Due: 2020-11-30
- Completed: 2021-02-01
The Data Release Production science payload now includes the capability of performing “forced” photometry at the positions of known Objects on Processed Visit Images, as described in LDM-151 :cite:`LDM-151` §5.5.2. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
- WBS: 02C.04
- Level: 3
- Predecessors: F20F
- Successors: LDM-503-13a
- Due: 2020-11-30
- Completed: 2021-05-24
The Data Release Production science payload now includes the capability of generating multi-scale maps that describe LSST’s depth and efficiency at detecting different classes of object as part of a data release, as described in LDM-151 :cite:`LDM-151` §5.6.3. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithms being used is expected.
- WBS: 02C.04
- Level: 3
- Predecessors: F21S, DM-DRP-9, COMC-060200-10000
- Successors: LSST-1580
- Due: 2021-06-01
- Completed: 2021-08-31
The Calibration Products Production science payload is now capable of producing an atmospheric transmission model based on observations from the Auxiliary Telescope, as described in LDM-151 :cite:`LDM-151` §4.6.1. This milestone does not presume that the Auxiliary Telescope itself is available for testing: it is satisfied by the availability of a pipeline that can process appropriate simulated or precursor data. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
- WBS: 02C.04
- Level: 3
- Predecessors: DM-DRP-27
- Successors: LDM-503-13a
- Due: 2021-08-31
- Completed: 2021-02-01
The Data Release Production science payload is now capable of finalizing the definition of Objects which fall within the overlap regions at the edges of tracts and patches, as described in LDM-151 :cite:`LDM-151` §5.4. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-27: Object generation: association and assembly of (DIA, coadd, etc) sources to form objects.
- WBS: 02C.04
- Level: 3
- Predecessors: DM-DRP-28
- Successors: LDM-503-15a, DM-DRP-26
- Due: 2021-08-31
- Completion pending
The Data Release Production science payload now includes the capability to build Objects by cross-matching the Source and DIASource tables, as described in LDM-151 :cite:`LDM-151` §5.3.2. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
- WBS: 02C.04
- Level: 3
- Predecessors: S21F, DM-AP-11
- Successors: LDM-503-13a, DM-DRP-27
- Due: 2021-08-31
- Completed: 2021-04-14
The Data Release Production science payload now includes the capability to generate difference images, and to perform source detection and characterization on those images, as described in LDM-151 :cite:`LDM-151` §5.2.5. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-35: Simultaneous measurement across a suite of coadds representing different bandpasses, epocs, and flavors.
- WBS: 02C.04
- Level: 3
- Successors: DM-DRP-31
- Due: 2021-08-31
- Completed: 2021-10-29
The Data Release Production science payload now includes the capability to perform consistent measurement of all Objects in a patch across multiple coadds, as described in LDM-151 :cite:`LDM-151` §5.3.4. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithms being used is expected.
DM-DRP-24: Physically motivated PSF model, including separate characterization of contributions from the atmosphere and the telescope system.
- WBS: 02C.04
- Level: 3
- Predecessors: LSST-1520
- Successors: LSST-1580
- Due: 2024-11-01
- Completion pending
Per LDM-151 :cite:`LDM-151` §6.11.3, the PSF model used by the Data Release Production science payload is now decomposed into separate contributions from the telescope optics and the atmosphere.
- WBS: 02C.04
- Level: 3
- Predecessors: LSST-1520, DM-DRP-35
- Successors: DM-DRP-36
- Due: 2024-11-01
- Completion pending
The Data Release Production science payload now includes the capability of calculating photometric redshifts as part of a data release, as (briefly) described in LDM-151 :cite:`LDM-151` §5.6.5. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
- WBS: 02C.04
- Level: 3
- Predecessors: DM-AP-17, DM-DRP-31
- Successors: LSST-1580
- Due: 2024-11-01
- Completion pending
The Data Release Production science payload now generates SSObjects, by delegating to the Solar System Processing (SSP) pipeline being delivered by the Alert Production team, as described in LDM-151 :cite:`LDM-151` §5.6.1. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
![_static/graph_02C.05.png](/lsst-dm/dmtn-158/raw/main/_static/graph_02C.05.png)
Relationships between milestones in WBS 02C.05 and their immediate predecessors and successors. Ellipses correspond to milestones within this WBS element; rectangles to those in other elements. Blue milestones have been completed; orange milestones are overdue.
- WBS: 02C.05.05
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
- WBS: 02C.05.01
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
- WBS: 02C.05.02
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
- WBS: 02C.05.03
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
- WBS: 02C.05.04
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
- WBS: 02C.05.01
- Level: 3
- Due: 2014-10-14
- Completed: 2014-10-14
Warning
No description available
- WBS: 02C.05.01
- Level: 3
- Due: 2014-12-02
- Completed: 2014-12-02
Warning
No description available
- WBS: 02C.05.01
- Level: 3
- Due: 2015-03-11
- Completed: 2015-03-11
Warning
No description available
- WBS: 02C.05.05
- Level: 3
- Due: 2015-03-20
- Completed: 2015-03-20
Warning
No description available
- WBS: 02C.05.01
- Level: 3
- Due: 2015-07-28
- Completed: 2015-11-17
Warning
No description available
- WBS: 02C.05.05
- Level: 3
- Due: 2015-07-31
- Completed: 2015-11-17
Warning
No description available
- WBS: 02C.05.02
- Level: 3
- Due: 2015-08-31
- Completed: 2015-11-17
Warning
No description available
- WBS: 02C.05.02
- Level: 3
- Due: 2015-08-31
- Completed: 2016-11-02
Warning
No description available
- WBS: 02C.05.01
- Level: 3
- Due: 2016-02-24
- Completed: 2016-04-08
Warning
No description available
- WBS: 02C.05
- Level: 3
- Successors: LDM-503-01
- Due: 2016-09-30
- Completed: 2017-11-30
Warning
No description available
- WBS: 02C.05.01
- Level: 3
- Predecessors: DMTC-0000-0030
- Successors: S17S
- Due: 2016-11-30
- Completed: 2017-07-31
Warning
No description available
DM-SUIT-2: Search WISE coaded data single exposure images in PDAC (the images are from IRSA at IPAC, not NCSA)
- WBS: 02C.05
- Level: 3
- Predecessors: DM-DAX-2
- Successors: LDM-503-01
- Due: 2017-07-31
- Completed: 2017-11-30
Warning
No description available
- WBS: 02C.05
- Level: 3
- Predecessors: DM-DAX-1
- Successors: LDM-503-01
- Due: 2017-11-30
- Completed: 2017-11-30
Warning
No description available
- WBS: 02C.05
- Level: 3
- Successors: LDM-503-01
- Due: 2017-11-30
- Completed: 2017-11-30
Warning
No description available
Warning
No description available
Warning
No description available
Warning
No description available
- WBS: 02C.05
- Level: 3
- Successors: DM-SUIT-10
- Due: 2018-11-30
- Completed: 2020-05-29
Portal is integrated with LSST-provided WebDAV or VOSpace service exposing the User File Workspace. Portal provides functions for saving image and catalog query results to the logged-in user's workspace, with the user's identity correctly applied. Portal provides functions for accessing data in the user's workspace and displaying it using the Portal's image and table visualization tools, as well as using data from the workspace in other Portal contexts where a file can be uploaded, e.g., to perform a multi-object query. (NB: Still achievable post-DM-10, though only with WebDAV.).
- WBS: 02C.05
- Level: 3
- Predecessors: DM-NCSA-2, DM-NCSA-3, DM-DAX-2, DM-DAX-5
- Successors: LDM-503-09
- Due: 2019-02-28
- Completed: 2022-06-30
Portal provides access to a collection of public-release HSC data processed by LSST DM, including calibrated single-epoch images, coadds, and catalogs (including at least an Object-like catalog). Access is obtained via IVOA interfaces including TAP for catalogs and ObsTAP for image metadata. (NB: Still achievable post-DM-10).
- WBS: 02C.05
- Level: 3
- Predecessors: S19F
- Successors: DM-SUIT-10
- Due: 2019-05-31
- Completed: 2019-05-31
Portal is integrated with NCSA-provided federated-identity authentication and authorization system: the Portal recognizes that a user is logged in and displays that state, and passes the user's identity along to LSST data services that it accesses. (NB: Still achievable post-DM-10) Claimed in May, based on installation on lsst-lsp-int.
- WBS: 02C.05
- Level: 3
- Predecessors: S19F, DM-SUIT-7, DM-SUIT-8
- Successors: LDM-503-11a
- Due: 2019-05-31
- Completed: 2020-06-30
Portal software is adapted for deployment in Kubernetes. The set of container images required for deployment is documented in an LTD-style manner. Configuration files for Kubernetes are provided in Github and documented to a level that permits deployments to be performed by non-IPAC staff. (NB: Still achievable post-DM-10).
![_static/graph_02C.06.png](/lsst-dm/dmtn-158/raw/main/_static/graph_02C.06.png)
Relationships between milestones in WBS 02C.06 and their immediate predecessors and successors. Ellipses correspond to milestones within this WBS element; rectangles to those in other elements. Blue milestones have been completed; orange milestones are overdue.
- WBS: 02C.06.02
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2015-11-17
Warning
No description available
- WBS: 02C.06.02
- Level: 3
- Predecessors: DLP-834
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
- WBS: 02C.06.02
- Level: 3
- Predecessors: LSST-1440
- Successors: DLP-835
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
- WBS: 02C.06.02
- Level: 3
- Due: 2014-11-25
- Completed: 2015-11-17
Warning
No description available
- WBS: 02C.06.02
- Level: 3
- Due: 2014-11-25
- Completed: 2015-11-17
Warning
No description available
- WBS: 02C.06.02
- Level: 3
- Due: 2015-05-29
- Completed: 2015-11-17
Warning
No description available
- WBS: 02C.06.01
- Level: 3
- Due: 2015-05-29
- Completed: 2015-11-17
Warning
No description available
- WBS: 02C.06.02
- Level: 3
- Due: 2015-08-31
- Completed: 2015-09-01
Warning
No description available
- WBS: 02C.06.02
- Level: 3
- Due: 2015-10-29
- Completed: 2015-10-29
Warning
No description available
- WBS: 02C.06.02
- Level: 3
- Due: 2015-11-25
- Completed: 2016-01-12
Warning
No description available
- WBS: 02C.06.02
- Level: 3
- Due: 2016-02-24
- Completed: 2017-05-26
Warning
No description available
- WBS: 02C.06.01
- Level: 3
- Due: 2016-11-30
- Completed: 2021-05-31
Warning
No description available
- WBS: 02C.06.02
- Level: 3
- Predecessors: DMTC-0000-3000, S17F
- Due: 2017-05-31
- Completed: 2018-06-29
Warning
No description available
- WBS: 02C.06
- Level: 3
- Successors: LDM-503-09, LDM-503-10a, DM-SUIT-2, DM-SUIT-5
- Due: 2017-07-31
- Completed: 2019-11-29
An IVOA TAP service supporting both synchronous and asynchronous query models, integrated with the LSP authentication architecture, and able to access catalog data hosted in a downstream in Qserv instance.
- WBS: 02C.06
- Level: 3
- Successors: LDM-503-01, DM-SUIT-1
- Due: 2017-11-30
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.06
- Level: 3
- Successors: DM-NCSA-9, LDM-503-03
- Due: 2017-11-30
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.06.02
- Level: 3
- Predecessors: S17F, F17F
- Successors: DLP-725
- Due: 2017-11-30
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.06.01
- Level: 3
- Predecessors: F17F, DLP-473
- Successors: S18S
- Due: 2017-11-30
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.06.02
- Level: 3
- Successors: F20F
- Due: 2017-12-01
- Completed: 2019-08-30
Warning
No description available
- WBS: 02C.06
- Level: 3
- Successors: LSST-1580
- Due: 2018-03-30
- Completed: 2018-05-31
Warning
No description available
Demonstrate Butler configuration able to gather all data pertaining to a particular object, such as retrieving cutouts from all warps at a given box on a skymap.
- WBS: 02C.06
- Level: 3
- Predecessors: DM-DRP-11, DM-DAX-10
- Successors: DM-NCSA-3, LDM-503-09, DM-SUIT-5, DM-DRP-2
- Due: 2019-02-28
- Completed: 2019-02-28
Existing Qserv ingest tooling is highly manual and poorly parallelized. Develop new tooling to address these issues and support ingest campaigns at the scale needed for DRP.
- WBS: 02C.06
- Level: 3
- Predecessors: DM-DAX-12
- Successors: DM-DAX-13
- Due: 2020-11-30
- Completed: 2020-06-30
Given a stood-up data backbone instance, demonstrate instantiation/configuration of a Butler Gen3 instance capable of retrieving images from that backbone instance. (As currently conceived, the data backbone is either a GPFS filesystem or object store, in combination with metadata that is a superset of that maintained in a Butler Gen3 registry. Depending on particular technologies and implementation strategies chosen for the data backbone, this may be either a "simple matter of configuration" of existing Butler connectors, or may require some additional custom connectors to be written.).
- WBS: 02C.06
- Level: 3
- Predecessors: F18F, DM-DAX-12
- Successors: DM-DRP-12, DM-DRP-13, DM-DRP-21
- Due: 2020-11-30
- Completed: 2020-06-30
Demonstrate a functional PipelineTask with scatter/gather functionality, such as Jointcal, SkyCorrect, or FGCM.
- WBS: 02C.06
- Level: 3
- Predecessors: F20F
- Successors: DM-NCSA-15, DM-NCSA-22, DM-DAX-7, DM-DAX-8, DM-DAX-9, DM-DAX-13
- Due: 2020-11-30
- Completed: 2020-11-30
Generation 3 middleware, consisting of Butler updates and the PipelineTask framework, are now able to support existing science payloads with no loss of functionality over previous versions. That is, Gen 3 may not be feature complete, but Gen 2 can be retired with no functionality regressions across the subsystem.
Warning
No description available
- WBS: 02C.06
- Level: 3
- Predecessors: S21F, DM-DAX-7, DM-DAX-12
- Successors: LSST-1580, LDM-GEN3
- Due: 2021-05-31
- Completed: 2022-05-31
The Generation 2 middleware is deprecated, and may be removed from the codebase. No current science payload and no current execution service makes use of it.
- WBS: 02C.06
- Level: 3
- Successors: LSST-1580
- Due: 2024-01-11
- Completion pending
Warning
No description available
- WBS: 02C.06
- Level: 3
- Predecessors: LSST-1520, DM-DAX-12, DM-DAX-14, COMC-060200-20930
- Successors: LDM-503-17a
- Due: 2024-11-01
- Completion pending
Warning
No description available
![_static/graph_02C.07.png](/lsst-dm/dmtn-158/raw/main/_static/graph_02C.07.png)
Relationships between milestones in WBS 02C.07 and their immediate predecessors and successors. Ellipses correspond to milestones within this WBS element; rectangles to those in other elements. Blue milestones have been completed; orange milestones are overdue.
- WBS: 02C.07.01
- Level: 3
- Due: 2014-11-19
- Completed: 2014-11-19
Warning
No description available
- WBS: 02C.07.01
- Level: 3
- Due: 2014-11-21
- Completed: 2014-11-21
Warning
No description available
- WBS: 02C.07.03
- Level: 3
- Due: 2015-01-29
- Completed: 2015-01-29
Warning
No description available
- WBS: 02C.07.04
- Level: 3
- Due: 2015-02-02
- Completed: 2015-02-02
Warning
No description available
- WBS: 02C.07.04
- Level: 3
- Due: 2015-02-02
- Completed: 2016-07-15
Warning
No description available
- WBS: 02C.07.02
- Level: 3
- Successors: DLP-556
- Due: 2015-05-28
- Completed: 2015-01-26
Warning
No description available
- WBS: 02C.07.04
- Level: 3
- Due: 2015-05-29
- Completed: 2015-05-29
Warning
No description available
- WBS: 02C.07.04
- Level: 3
- Due: 2015-07-30
- Completed: 2015-07-30
Warning
No description available
- WBS: 02C.07.00
- Level: 3
- Due: 2015-08-26
- Completed: 2015-08-26
Warning
No description available
- WBS: 02C.07.01
- Level: 3
- Due: 2015-08-26
- Completed: 2015-08-26
Warning
No description available
- WBS: 02C.07.00
- Level: 3
- Due: 2015-08-31
- Completed: 2015-08-31
Warning
No description available
- WBS: 02C.07.02
- Level: 3
- Due: 2015-08-31
- Completed: 2016-06-07
Warning
No description available
- WBS: 02C.07.02
- Level: 3
- Due: 2015-08-31
- Completed: 2015-08-31
Warning
No description available
- WBS: 02C.07.02
- Level: 3
- Due: 2015-08-31
- Completed: 2015-08-31
Warning
No description available
- WBS: 02C.07.03
- Level: 3
- Due: 2015-08-31
- Completed: 2015-08-31
Warning
No description available
- WBS: 02C.07.04
- Level: 3
- Due: 2015-08-31
- Completed: 2015-08-31
Warning
No description available
- WBS: 02C.07.01
- Level: 3
- Successors: DLP-358
- Due: 2015-09-29
- Completed: 2016-06-15
Warning
No description available
- WBS: 02C.07.01
- Level: 3
- Successors: DLP-566
- Due: 2015-09-29
- Completed: 2015-09-29
Warning
No description available
- WBS: 02C.07.04
- Level: 3
- Due: 2016-01-22
- Completed: 2016-07-15
Warning
No description available
- WBS: 02C.07.02
- Level: 3
- Successors: DLP-412
- Due: 2016-02-05
- Completed: 2016-06-07
Warning
No description available
- WBS: 02C.07.02
- Level: 3
- Successors: S17S
- Due: 2016-02-22
- Completed: 2016-06-07
Warning
No description available
- WBS: 02C.07.02
- Level: 3
- Successors: S17S
- Due: 2016-02-22
- Completed: 2016-07-15
Warning
No description available
- WBS: 02C.07.00
- Level: 3
- Successors: DLP-864
- Due: 2016-02-24
- Completed: 2016-06-07
Warning
No description available
DLP-358: Refinement of facility integration plan and traceability of science and operational requirements
- WBS: 02C.07.01
- Level: 3
- Predecessors: DLP-357
- Due: 2016-02-24
- Completed: 2016-04-08
Warning
No description available
- WBS: 02C.07.01
- Level: 3
- Successors: DLP-566
- Due: 2016-02-24
- Completed: 2016-06-07
Warning
No description available
- WBS: 02C.07.04
- Level: 3
- Due: 2016-02-24
- Completed: 2016-06-07
Warning
No description available
DLP-431: Refinement of facility integration plan and traceability of science and operational requirements
- WBS: 02C.07.04
- Level: 3
- Due: 2016-02-24
- Completed: 2016-07-15
Warning
No description available
- WBS: 02C.07.03
- Level: 3
- Due: 2016-02-29
- Completed: 2016-07-15
Warning
No description available
- WBS: 02C.07.01
- Level: 3
- Predecessors: DMTC-0000-0030
- Successors: F17F
- Due: 2016-11-30
- Completed: 2017-09-01
Warning
No description available
- WBS: 02C.07.01
- Level: 3
- Predecessors: DMTC-0000-0030
- Successors: F17F
- Due: 2016-11-30
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.07.02
- Level: 3
- Predecessors: DLP-411, DMTC-0000-0030
- Successors: S18S
- Due: 2016-11-30
- Completed: 2017-09-01
Warning
No description available
- WBS: 02C.07
- Level: 3
- Predecessors: DM-DRP-1
- Successors: DM-NCSA-2, LDM-503-02
- Due: 2017-05-31
- Completed: 2017-11-01
Warning
No description available
DM-NCSA-2: Provide access to results of regular reprocessing (NB the form this takes depends upon available DAX functionality)
- WBS: 02C.07
- Level: 3
- Predecessors: DM-NCSA-1
- Successors: LDM-503-02, DM-SUIT-5
- Due: 2017-05-31
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.07
- Level: 3
- Successors: DM-NCSA-29, LSST-1190
- Due: 2017-09-29
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.07.00
- Level: 3
- Predecessors: DLP-469
- Successors: S18F
- Due: 2017-11-30
- Completed: 2017-11-01
Warning
No description available
Warning
No description available
Warning
No description available
Warning
No description available
Warning
No description available
- WBS: 02C.07.04
- Level: 3
- Predecessors: F17F
- Due: 2017-11-30
- Completed: 2018-04-30
Warning
No description available
- WBS: 02C.07.04
- Level: 3
- Predecessors: F17F
- Due: 2017-11-30
- Completed: 2018-04-30
Warning
No description available
- WBS: 02C.07
- Level: 3
- Due: 2017-12-01
- Completed: 2017-12-01
Time-based milestone marking the start of NCSA's Spring 2018 development cycle.
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-04b, LSST-1160
- Due: 2017-12-29
- Completed: 2017-12-01
Warning
No description available
- WBS: 02C.07
- Level: 3
- Predecessors: DM-NCSA-28
- Successors: LSST-1200
- Due: 2017-12-29
- Completed: 2018-03-31
Warning
No description available
DM-NCSA-6: Ability to transfer files originating from Tucson to NCSA and ingest files at NCSA, including metadata and provenance
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-04b
- Due: 2018-03-05
- Completed: 2018-10-31
Warning
No description available
DM-NCSA-5: Level 1 archiving system able to acquire pixel data from the Aux Tel DAQ, header metadata via OCS, assemble FITS image,
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-04b
- Due: 2018-03-30
- Completed: 2018-05-31
Warning
No description available
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-04b
- Due: 2018-03-30
- Completed: 2018-06-29
Warning
No description available
DM-NCSA-9: Test instance of alert distribution hosting service and L1 database in Development & Integration Enclave
- WBS: 02C.07
- Level: 3
- Predecessors: DM-DAX-6
- Successors: LDM-503-05, DM-AP-6
- Due: 2018-08-31
- Completed: 2019-05-31
Hosting an instance of the alert distribution service delivered from University of Washington on our test containerized application management service platform, running feeds from the pipeline to the distribution services. Note: This was informally tied to LDM-503-05, which was de-scoped to a small demonstration of running an instance of Kafka at NCSA, so no L1 database was needed. We believe this was completed in August 2018.
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-06
- Due: 2018-09-25
- Completed: 2019-05-31
The capability to use the existing OCS/CCS to command data acquisition and hand-off to a test Observatory Operations Data Service (OODS).
DM-NCSA-3: Provide database for metadata, provenance, location and demonstrate ingest at small scale
- WBS: 02C.07
- Level: 3
- Predecessors: DM-DAX-5
- Successors: DM-NCSA-4, LDM-503-02, DM-SUIT-5, DM-DRP-2
- Due: 2019-02-28
- Completed: 2017-11-01
Warning
No description available
DM-NCSA-4: Minimal support for the small operational schema including file metadata and provenance for every file, and record of in
- WBS: 02C.07
- Level: 3
- Predecessors: DM-NCSA-3, LDM-503-02
- Successors: LDM-503-04
- Due: 2019-02-28
- Completed: 2018-06-29
Warning
No description available
- WBS: 02C.07
- Level: 3
- Predecessors: DM-DRP-1
- Successors: LDM-503-09, LDM-503-11, LDM-503-11a
- Due: 2019-03-29
- Completed: 2019-06-13
Process ComCam-scale data through the ISR pipeline to generate QC parameters used by the observatory.
- WBS: 02C.07.09
- Level: 4
- Predecessors: T&SC-6500-8100
- Due: 2019-05-08
- Completed: 2019-04-30
Arrival at NCSA of hardware to support ComCam testing and integration.
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-08
- Due: 2019-05-14
- Completed: 2019-05-31
The Header builder integrated into OCS and demonstrated. Header builder has identified sources of information for all modes of observing with the Spectrograph.
- WBS: 02C.07.09
- Level: 4
- Due: 2019-06-20
- Completed: 2019-06-27
Date for ComCam support systems to ship from NCSA to Tucson.
- WBS: 02C.07.09
- Level: 4
- Due: 2019-06-28
- Completed: 2019-06-28
Date for Authentication and Authorization hardware to ship from NCSA to Chile.
- WBS: 02C.07.09
- Level: 4
- Successors: A4670
- Due: 2019-07-15
- Completed: 2019-07-17
Date for Base Data Center hardware to ship from NCSA to Chile.
DM-NCSA-11: Verified acquisition of raw and crosstalk-corrected exposures at raft scale, incl. correct metadata
- WBS: 02C.07
- Level: 3
- Predecessors: F18F, T&SC-5900-0400
- Successors: DLP-552, LDM-503-06
- Due: 2019-07-29
- Completed: 2020-06-30
Exercise the handoff between the L1 archiving and data backbone endpoint, including a monitoring service that tracks files that have been transferred and received.
- WBS: 02C.07.09
- Level: 4
- Successors: LDM-503-09, A5860
- Due: 2019-08-14
- Completed: 2019-08-01
ComCam Test Stand ready for access by NCSA staff.
- WBS: 02C.07.09
- Level: 4
- Successors: LDM-503-09
- Due: 2019-08-16
- Completed: 2019-08-24
End of travel to Chile to install hardware and systems at the Base Data Center.
- WBS: 02C.07.09
- Level: 4
- Predecessors: A4369.9
- Due: 2019-08-17
- Completed: 2019-08-17
Start of travel to Chile to install hardware and systems at the Base Data Center.
- WBS: 02C.07.09
- Level: 4
- Due: 2019-08-29
- Completed: 2019-08-29
Authorization and Authentication systems installed at the Summit.
- WBS: 02C.07
- Level: 3
- Predecessors: T&SC-5900-0400
- Successors: LDM-503-11a
- Due: 2019-09-06
- Completed: 2020-06-30
Implement a Service that acquires raw data from a camera at raft scale and sends to NCSA for ingestion into the Data Backbone. This is a preliminary milestone to demonstrate initial capabilities.
- WBS: 02C.07.05
- Level: 4
- Due: 2019-10-01
- Completed: 2019-10-01
Warning
No description available
- WBS: 02C.07
- Level: 3
- Due: 2020-01-03
- Completed: 2020-01-03
Warning
No description available
DM-NCSA-14: Data Backbone endpoints in Chile for ingestion and access, distribution over WAN, ingest at NCSA into custodial file sto
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-08
- Due: 2020-06-22
- Completed: 2021-11-17
Provide a data Backbone endpoint in Chile, allowing distribution over a wide-area network and ingestion at NCSA.
- WBS: 02C.07
- Level: 3
- Predecessors: DM-DAX-12
- Successors: LDM-503-08
- Due: 2020-11-30
- Completed: 2020-05-29
Demonstrate the ability to process offline Spectrograph data using a science pipeline in the Batch Processing Service. Output(s) will be available in the Data Backbone.
- WBS: 02C.07
- Level: 3
- Predecessors: DM-DAX-12
- Successors: LDM-503-11a
- Due: 2020-11-30
- Completed: 2020-08-31
Scientific and operational data products stored in the consolidated database during ComCam data processing are available for QA assessment of ComCam data through normal analysis access environments.
- WBS: 02C.07
- Level: 3
- Successors: LSST-1580
- Due: 2024-11-01
- Completed: 2023-05-31
Demonstrated running of processing campaigns in offline mode needed for the ComCam phase of commissioning to debug the instrument. Likely includes calibration, ISR, and other pipelines.
![_static/graph_02C.08.png](/lsst-dm/dmtn-158/raw/main/_static/graph_02C.08.png)
Relationships between milestones in WBS 02C.08 and their immediate predecessors and successors. Ellipses correspond to milestones within this WBS element; rectangles to those in other elements. Blue milestones have been completed; orange milestones are overdue.
- WBS: 02C.08.02
- Level: 2
- Predecessors: LSST-1440
- Due: 2015-06-11
- Completed: 2015-08-05
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Due: 2015-09-28
- Completed: 2015-04-30
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Due: 2015-10-01
- Completed: 2015-10-01
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-43
- Due: 2015-12-15
- Completed: 2015-12-15
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Due: 2015-12-15
- Completed: 2015-12-25
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8000-0760
- Due: 2015-12-16
- Completed: 2017-02-28
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-41
- Due: 2015-12-16
- Completed: 2015-12-16
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2010, DMTC-7400-2170
- Due: 2016-01-15
- Completed: 2016-02-29
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-41
- Due: 2016-01-15
- Completed: 2016-01-15
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Due: 2016-03-15
- Completed: 2016-03-31
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8000-0910
- Successors: DMTC-8000-0806
- Due: 2016-04-15
- Completed: 2016-05-02
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-45
- Due: 2016-04-15
- Completed: 2016-06-17
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2290
- Due: 2016-06-01
- Completed: 2016-03-31
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-63
- Due: 2016-06-01
- Completed: 2016-10-01
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Due: 2016-09-28
- Completed: 2016-10-01
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Due: 2016-09-30
- Completed: 2016-09-30
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: DLP-45
- Due: 2017-01-02
- Completed: 2017-03-15
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2210
- Due: 2017-02-28
- Completed: 2017-05-19
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-37
- Due: 2017-02-28
- Completed: 2017-02-28
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Due: 2017-04-24
- Completed: 2017-03-23
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-40
- Due: 2017-06-01
- Completed: 2017-06-30
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Due: 2017-06-30
- Completed: 2017-04-28
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Successors: DMTC-7400-2480, DMTC-7400-2130
- Due: 2017-07-31
- Completed: 2017-08-01
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Due: 2017-08-18
- Completed: 2017-12-01
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Successors: DMTC-7400-2130, DLP-40, DLP-65
- Due: 2017-09-29
- Completed: 2017-09-15
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Due: 2017-09-29
- Completed: 2017-09-01
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2420
- Successors: DMTC-8000-0818, DMTC-7400-2510
- Due: 2017-10-30
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2480
- Due: 2017-11-30
- Completed: 2017-12-01
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2480
- Due: 2017-11-30
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2420, DMTC-7400-2330
- Due: 2017-11-30
- Completed: 2017-12-01
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8000-0826
- Due: 2018-03-02
- Completed: 2017-12-31
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-44
- Due: 2018-03-02
- Completed: 2018-03-02
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: S17F
- Successors: DMTC-8000-0836
- Due: 2018-03-14
- Completed: 2018-01-12
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2250, DMTC-7400-2330
- Due: 2018-03-14
- Completed: 2017-12-22
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2330
- Due: 2018-03-14
- Completed: 2018-03-31
Warning
No description available
- WBS: 02C.08.01
- Level: 1
- Predecessors: DLP-559
- Successors: LDM-503-08, COMC-0620-2050
- Due: 2018-03-27
- Completed: 2018-04-02
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Due: 2018-04-02
- Completed: 2018-06-01
Warning
No description available
DMTC-8000-0836: La Serena to Santiago with live traffic and uptime over LSST Lambda Ready - Complete
- WBS: 02C.08.03
- Level: 3
- Predecessors: DLP-61
- Due: 2018-05-11
- Completed: 2019-07-23
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-36
- Due: 2018-06-29
- Completed: 2018-06-29
Warning
No description available
Warning
No description available
- WBS: 02C.08.03
- Level: 2
- Predecessors: T&SC-2600-1545
- Successors: LDM-503-08
- Due: 2018-09-28
- Completed: 2018-03-05
Warning
No description available
- WBS: 02C.08.00
- Level: 3
- Predecessors: T&SC-2600-1545
- Successors: LDM-503-08
- Due: 2018-09-28
- Completed: 2018-04-02
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Due: 2018-10-01
- Completed: 2018-10-31
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-33
- Due: 2018-10-26
- Completed: 2019-05-31
Contract Deliverable Report #4 Spectrum Complete. Test of first data passing over Santiago - Boca Raton Spectrum link.
- WBS: 02C.08.01
- Level: 4
- Predecessors: T&SC-0400-1600
- Due: 2018-11-26
- Completed: 2019-03-18
Warning
No description available
- WBS: 02C.08.01
- Level: 4
- Due: 2019-02-12
- Completed: 2019-06-30
Externally linked to TS milestone for full occupancy of Base Data Center, including all construction, utilities, access and dust control.
DMTC-8000-0870: Report on functional fiber, including uptime, 1st year functional milestone - Complete
- WBS: 02C.08.03
- Level: 3
- Due: 2019-03-22
- Completed: 2019-07-23
Contract Deliverable Report #8 Report on functional fiber, including uptime, 1st year functional milestone - Complete. Covers first year of operational service of La Serena - Santiago primary fiber, including availability and outage information.
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8100-2090, DMTC-8100-2112
- Successors: DLP-468
- Due: 2019-04-22
- Completed: 2018-06-01
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-36
- Due: 2019-04-22
- Completed: 2019-02-01
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Due: 2019-05-08
- Completed: 2019-02-13
Warning
No description available
- WBS: 02C.08.01
- Level: 4
- Due: 2019-05-31
- Completed: 2019-10-31
Externally linked to TS milestone for installation of furniture of Base Office Building and Base Data Center. All cabling to connect offices to Base LAN has been received.
- WBS: 02C.08.03
- Level: 3
- Due: 2019-06-05
- Completed: 2019-03-25
Contract Deliverable Report #10 Technical Implementation Plan for 40Gbps diverse path - Complete. Covers the fiber and equipment, ownership/service levels for La Serena - Santiago secondary path.
- WBS: 02C.08.03
- Level: 2
- Successors: LDM-503-11
- Due: 2019-07-15
- Completed: 2020-01-31
Installed the Base LAN equipment in the Base Date Center and Base Office Building technical closets, and cabling connecting them for the Base Campus and Control Networks. Tested with data volumes and access points equivalent to operational staffing and control servers for ATS observing. (Level 2 equivalent of Level 3 milestone IT-725-M).
- WBS: 02C.08.01
- Level: 4
- Successors: LDM-503-10
- Due: 2019-07-29
- Completed: 2021-08-20
Installed the Base LAN equipment in the Base Data Center and Base Office Building technical closets, and cabling connecting them for the Base Campus and Control Networks. Tested with data volumes and access points equivalent to operational staffing and control servers for ATS observing. (Level 3 equivalent of Level 2 milestone DM-NET-4).
- WBS: 02C.08.03
- Level: 3
- Due: 2019-09-30
- Completed: 2019-12-31
Level of effort management task, annual report delivered, covering all activities, meetings, conferences/workshops, circuits, tools, tests, staffing, budget/expenditures.
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8200-0510
- Due: 2019-10-01
- Completed: 2019-11-01
Miami - Atlanta, and ESNet Atlanta - Chicago 2 x 20 Gbps path diverse circuits available and tested at capacity.
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8200-0510
- Due: 2019-10-01
- Completed: 2019-11-14
Boca Raton - Atlanta and ESNet Atlanta - Chicago 2 x 20 Gbps path diverse circuits available and tested at capacity.
- WBS: 02C.08.03
- Level: 3
- Due: 2019-10-01
- Completed: 2019-11-14
ESNet Atlanta - Chicago 2 x 20 Gbps path diverse circuits available and tested at capacity.
- WBS: 02C.08.03
- Level: 3
- Due: 2020-07-02
- Completed: 2020-02-19
Contract Deliverable Report #6 100G managed ring Contract Delivery #6 Complete. Covers availability and outages.
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8100-2530, DMTC-6800-1325, S18F
- Successors: LSST-1580
- Due: 2020-09-14
- Completed: 2019-08-31
Spectrum link operational at 100 Gbps from Santiago - Boca Raton, including terrestrial segment from Santiago - Sao Paolo, and Monet submarine cable from Sao Paolo - Boca Raton.
- WBS: 02C.08.00
- Level: 4
- Successors: DLP-33
- Due: 2020-09-14
- Completed: 2020-02-28
Warning
No description available
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8000-0990, S19F
- Due: 2020-09-30
- Completed: 2021-08-31
Both primary (100 Gbps) and secondary (40 - 100 Gbps) circuits from La Serena - Santiago are operational and tested with loads to full capacity.
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-46
- Due: 2020-09-30
- Completed: 2021-08-31
Contract Deliverable Report #11 Full capacity La Serena to Santiago over Primary link AND Secondary link - Complete. Covers the results of testing of the La Serena - Santiago primary and secondary paths.
- WBS: 02C.08.03
- Level: 3
- Due: 2020-09-30
- Completed: 2020-09-30
Level of effort management task, annual report delivered, covering all activities, meetings, conferences/workshops, circuits, tools, tests, staffing, budget/expenditures.
- WBS: 02C.08.01
- Level: 3
- Predecessors: F20F
- Successors: LSST-1580, CAMM8350
- Due: 2020-11-30
- Completed: 2020-11-30
Installed the Base LAN equipment in the Base Data Center and Base Office Building technical closets, and cabling connecting them for the Base Campus and Control Networks. Tested with data volumes and access points equivalent to operational staffing and control servers for full camera observing.
- WBS: 02C.08.02
- Level: 3
- Predecessors: DLP-36, F20F
- Successors: LDM-503-11
- Due: 2020-11-30
- Completed: 2020-11-30
Installed the Base LAN equipment in the Chilean DAC. Tested with data volumes and access points equivalent to anticipated DAC user workload contemporaneous with full camera observing.
- WBS: 02C.08.02
- Level: 3
- Predecessors: F20F
- Successors: LDM-503-11
- Due: 2020-11-30
- Completed: 2020-11-30
Installed the Base LAN equipment in the Chilean DAC. Tested with data volumes and access points equivalent to anticipated DAC user workload contemporaneous with commissioning camera observing.
- WBS: 02C.08
- Level: 2
- Predecessors: DLP-464, COMC-0021
- Successors: CAMM8330, CAMM8340, COMC-0620-2240
- Due: 2020-12-21
- Completed: 2021-02-01
All segments of the Base - Archive Network, including La - Serena - Santiago - Sao Paolo - Miami/Boca Raton - Chicago - Champaign are operationally available at 100 Gbps line rate (effective rate is typically lower, ~ 80%).
- WBS: 02C.08.01
- Level: 3
- Predecessors: F18F
- Successors: CAMM8340, DM-NET-5
- Due: 2020-12-21
- Completed: 2020-11-30
Installed the Base LAN equipment in the Base Data Center and Base Office Building technical closets, and cabling connecting them for the Base Campus and Control Networks. Tested with data volumes and access points equivalent to operational staffing and control servers for commissioning camera observing.
- WBS: 02C.08.02
- Level: 3
- Predecessors: F18F
- Successors: LSST-1580, CAMM8330, CAMM8340
- Due: 2020-12-21
- Completed: 2020-11-30
Installed the Base LAN equipment in the Chilean DAC. Tested with data volumes and access points equivalent to anticipated DAC user workload contemporaneous with ATS observing.
- WBS: 02C.08.03
- Level: 3
- Due: 2021-06-30
- Completed: 2021-07-30
Contract Deliverable Report #7 100G managed ring Contract Delivery #7 Complete. Covers availability and outages.
- WBS: 02C.08.03
- Level: 3
- Due: 2021-09-01
- Completed: 2021-09-30
Level of effort management task, annual report delivered, covering all activities, meetings, conferences/workshops, circuits, tools, tests, staffing, budget/expenditures.
- WBS: 02C.08.00
- Level: 4
- Predecessors: SITCOM-130
- Successors: LSST-1580
- Due: 2025-03-06
- Completion pending
Warning
No description available
![_static/graph_02C.10.png](/lsst-dm/dmtn-158/raw/main/_static/graph_02C.10.png)
Relationships between milestones in WBS 02C.10 and their immediate predecessors and successors. Ellipses correspond to milestones within this WBS element; rectangles to those in other elements. Blue milestones have been completed; orange milestones are overdue.
Warning
No description available
- WBS: 02C.10.02
- Level: 3
- Successors: DLP-337
- Due: 2015-08-31
- Completed: 2016-04-08
Warning
No description available
- WBS: 02C.10.02
- Level: 3
- Predecessors: DLP-340
- Due: 2015-12-29
- Completed: 2016-04-08
Warning
No description available
- WBS: 02C.10.02
- Level: 3
- Predecessors: DLP-340
- Successors: DLP-337
- Due: 2015-12-29
- Completed: 2016-04-08
Warning
No description available
Warning
No description available
- WBS: 02C.10.02
- Level: 3
- Due: 2016-02-29
- Completed: 2016-05-31
Warning
No description available
- WBS: 02C.10.02
- Level: 3
- Due: 2016-02-29
- Completed: 2016-05-31
Warning
No description available
- WBS: 02C.10.02
- Level: 3
- Due: 2016-08-31
- Completed: 2017-07-25
Warning
No description available
- WBS: 02C.10.02
- Level: 3
- Successors: LDM-503-01, DM-SQRE-2
- Due: 2017-08-31
- Completed: 2017-11-01
Warning
No description available
- WBS: 02C.10.02
- Level: 3
- Predecessors: F17F
- Due: 2017-11-30
- Completed: 2017-11-01
Warning
No description available
Warning
No description available
DM-SQRE-2: Notebook service capabilities are suitable for the commissioning team to develop notebooks for its needs
- WBS: 02C.10.02
- Level: 3
- Predecessors: DM-SQRE-1
- Successors: LDM-503-09, DM-SQRE-3
- Due: 2018-11-30
- Completed: 2019-11-29
Members of the integration and commissioning team are able to develop notebooks in nublado that are capable of the interactive data exploration that is suitable to their needs to support ComCam commissioning. Data is available via a Butler to a mounted filesystem. They are able to work effectively, though in some cases their user experience can be improved. They are primarily trained in person by bootcamps and may require extensive support via Slack. The service may be intermittently unavailable due to engineering work.
- WBS: 02C.10.02
- Level: 3
- Predecessors: DM-SQRE-2
- Successors: LDM-503-12, DM-SQRE-4
- Due: 2020-02-27
- Completed: 2020-01-30
Members of the integration and commissioning team as well as science pipelines developers use nublado to support their interactive data exploration needs relating to ComCam commissioning. They are able to work effectively though in some cases their user experience can be improved. Access to EFD data is easily available from notebooks. Data is available via Butler to a mounted filesystem. There is a curated library of notebooks modeling common tasks and a way to automatically verify that they are in working condition. Users can refer to documentation for answers to common problems. The service is stable and interruptions to the service are primarily notified well in advance and co-ordinated with the commissioning team to minimize disruption to the extent that the underlying infrastructure permits it.
- WBS: 02C.10.02
- Level: 3
- Predecessors: F20F
- Successors: LSST-1580, DM-SQRE-7
- Due: 2020-11-30
- Completed: 2022-02-28
Warning
No description available
- WBS: 02C.10.02
- Level: 3
- Predecessors: F20F, DM-SQRE-6
- Successors: LSST-1580
- Due: 2020-11-30
- Completed: 2022-06-30
Warning
No description available
- WBS: 02C.10.02
- Level: 3
- Predecessors: DM-SQRE-3
- Successors: LDM-503-14
- Due: 2023-02-28
- Completion pending
Science pipeline developers and members of the verification and validation science team use nublado to support their interactive data exploration needs relating to ComCam commissioning. They are able to work effectively though in some cases their user experience can be improved. As well as access to EFD, catalogue and pixel data, they have access to any available APIs to the workflow/batch system for non-trivial data processing. There are curated libraries of continuously integrated notebooks modeling common tasks and they is a reasonable workflow to allow Github-based collaboration on those notebooks. Users can refer to documentation for how to get started and for answers to common problems. The service is stable with minimal interruptions, but may not always scale well to large number of users.
- WBS: 02C.10.02
- Level: 3
- Predecessors: LSST-1560
- Successors: LSST-1580
- Due: 2025-03-06
- Completion pending
Members of the science collaborations or other non-project staff with access to data use nublado to support their interactive scientific data exploration. They are able to share data with each other using LSP sharing mechanisms and can access data without a direct filesystem mount (eg VO services, remote Butler etc). The service scales well to large number of users provided the infrastructure is sized for them. Users can primarily rely on documentation for support, and use a helpdesk system for questions. There is robust functionality for performing large distributed catalog operations and for visually exploring LSSTCam sized images.
![_static/graph_02C.11.png](/lsst-dm/dmtn-158/raw/main/_static/graph_02C.11.png)
Relationships between milestones in WBS 02C.11 and their immediate predecessors and successors. Ellipses correspond to milestones within this WBS element; rectangles to those in other elements. Blue milestones have been completed; orange milestones are overdue.
- WBS: 02C.11
- Level: Undefined
- Predecessors: LSST-1440
- Due: 2022-10-03
- Completed: 2022-10-03
Warning
No description available
- WBS: 02C.11.03
- Level: 4
- Due: 2023-11-28
- Completion pending
Warning
No description available
- WBS: 02C.11.02
- Level: 4
- Successors: LSST-1580
- Due: 2023-12-06
- Completion pending
Warning
No description available
- WBS: 02C.11.01
- Level: 4
- Predecessors: SUMMIT-2976
- Successors: LSST-1580
- Due: 2023-12-07
- Completion pending
Warning
No description available